 Pengurasan Saluran Drainase Jl Galur Sari VIII Capai 95 Persen

Channel Dredging Work on Jl. Galur Sari VIII Touches 95 Percent

Process of channel dredging work on Jl. Galur Sari VIII RW 01 Utan Kayu Selatan, Matraman, East Jakarta has touched 95 percent.

Dredging work is done manually by deploying 10 personnel from Matraman SDA Unit every day

Matraman Water Resources (SDA) Unit Coordinator, Agus Sutono mentioned, channel with length about 250 meters has been dredged since early December and targeted to finish in the next three days.

"Dredging work is done manually by deploying 10 personnel from Matraman SDA Unit every day," he informed, Monday (12/28).

SDA Personnel in Kebayoran Baru Dredge Channel on Jl. Darmawangsa Raya

According to him, channel dredging is carried out because silt thickness reaches 30-50 centimeters and reduces channel's capacity.

"Later on, we hope this channel can hold more water thus it can prevent inundation around the location," he said.

Linked News
Popular News indeks
  1. Still Rp 3,500! No Fare Change for Transjakarta’s Kalideres–Soetta Route

    access_time01-08-2026 remove_red_eye552 personAldi Geri Lumban Tobing
  2. Jakarta Reaffirms Commitment to Preserving Cultural Heritage

    access_time31-07-2026 remove_red_eye528 personDessy Suciati
  3. New LapakMain Corner Creative Hub Inaugurated at Tunas Muda RPTRA, Kramat Pela

    access_time05-08-2026 remove_red_eye522 personTiyo Surya Sakti
  4. East Jakarta Repairs Fire Hydrants Damaged by Component Theft

    access_time31-07-2026 remove_red_eye466 personNurito
  5. Rano Karno Hopes Penjaringan Inspires a Citywide Quranic Movement

    access_time31-07-2026 remove_red_eye417 personBudhi Firmansyah Surapati