Progress of Belibis Retention Basin Construction has Reached 70 Percent

Belibis Retention Basin (Embung) construction progress now has reached 70 percent. It is located behind Lokbin Semper Public Housing, RW 04, Semper Barat Urban Village, Cilincing, North Jakarta. This retention basin is expected to control flood in the area.

We deploy 2 amphibious units, 3 excavator units belonging to SDA, and 1 excavator unit belonging to private companies

Cilincing Sub-district Water Resources (SDA) Unit Head, Tjahyono Budi Setiawan mentioned, this construction work has been carried out since October 24, 2020 and is targeted to be completed in April 2021.

"Current progress has reached 70 percent. But it is hampered due to pipeline owned by Pertamina. We continue to communicate and coordinate with Pertamina to find the solution," he said, Thursday (3/25).

Pesakih Public Housing Retention Basin Construction is Almost Completed

For the construction, his side collaborates with number of CSR companies, namely PT. Kawasan Berikat Nusantara (Persero), PT. Justus Sakti Raya, PT. Komatsu Indonesia, and PT. Superkrane Mitra Utama Tbk. Belibis Retention Basin is built on an area of 3.8 hectares which connected to Gubuk Genteng River and Sepatan River that leads to Cakung Drain.

"Dam width is 5 meters with depth 1.5 meters. While retention basin's depth is about 6 meters," he explained.

His side operated several heavy equipment to dredge mud, tidy up retention basin, and build dam.

"We deploy 2 amphibious units, 3 excavator units belonging to SDA, and 1 excavator unit belonging to private companies. We also deploy 2 operators from private companies and 10 Cilincing SDA Unit personnel," he informed.

Belibis Retention Basin is built to overcome flood and expected to hold more water in the surrounding area. It is also planned to be ecotourism area as citizen interaction place.

"According to plan, we will also build jogging track, culinary area, and green open space (RTH) in this location," he stated.

Linked News
Popular News indeks
  1. Commission E Urges Residents to Increase Role in Preventing DHF

    access_time19-12-2024 remove_red_eye1216 personDessy Suciati
  2. Transjakarta Adjusting Service as Simpang Pramuka and Rawamangun Bus Stops Closed

    access_time18-12-2024 remove_red_eye1054 personAldi Geri Lumban Tobing
  3. Transjakarta, Telkomsel to Improve Service for Customers

    access_time19-12-2024 remove_red_eye909 personAldi Geri Lumban Tobing
  4. Acting Governor Monitors Food Stock at Kramat Jati and Cipinang Markets

    access_time19-12-2024 remove_red_eye735 personFolmer
  5. TMII Prepares Stuntman Show to Music Concert

    access_time23-12-2024 remove_red_eye689 personNurito