Pengerukan Lumpur Saluran PHB Kencana Capai 70 Persen

Kencana Connecting Channel Dredging Work Targeted to Finish This Month

Dredging work on Kencana Connecting (PHB) Channel on Jalan Muria Dalam RT 06/02, Menteng Atas Urban Village, Setiabudi, South Jakarta which conducted since early January is targeted to be completed by the end of this month.

Its progress reaches 70 percent

Setiabudi Sub-district Water Resources (SDA) Sub-agency Unit Head, Yansori, dredging was carried out along 314 meters, from Jalan Putri RT 06/02, Pasar Manggis Urban Village until Jalan Warung Belek, RW 02 Menteng Atas Urban Village.

"Its progress reaches 70 percent. If it goes well, we are targeting it to finish by the end of March," he conveyed, Saturday (3/27).

PPSU Personnel Repair Drainage Cover on Jalan Duren Tiga

According to him, mud dredging work is carried out as deep as 30-100 centimeters. His side deployed 7 SDA Unit personnel and 1 excavator to dredge mud from the channel.

"Channel needs to be cleaned because the silt already dense thus it can't hold much water. After dredging, we hope it can increase its capacity," he stated.

Linked News
Popular News indeks
  1. Jakarta Endorses New Housing Project for Residents on Railway Embankments

    access_time28-03-2026 remove_red_eye2402 personDessy Suciati
  2. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye787 personTiyo Surya Sakti
  3. Pramono Calls for Enhanced Synergy at DPRD Post-Eid Gathering

    access_time30-03-2026 remove_red_eye695 personDessy Suciati
  4. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye633 personTiyo Surya Sakti
  5. Jakarta Environmental Sub-agency Clears Trash Buildup at Kramat Jati Wholesale Market

    access_time28-03-2026 remove_red_eye462 personNurito