Kencana Connecting Channel Dredging Work Targeted to Finish This Month

Dredging work on Kencana Connecting (PHB) Channel on Jalan Muria Dalam RT 06/02, Menteng Atas Urban Village, Setiabudi, South Jakarta which conducted since early January is targeted to be completed by the end of this month.

Its progress reaches 70 percent

Setiabudi Sub-district Water Resources (SDA) Sub-agency Unit Head, Yansori, dredging was carried out along 314 meters, from Jalan Putri RT 06/02, Pasar Manggis Urban Village until Jalan Warung Belek, RW 02 Menteng Atas Urban Village.

"Its progress reaches 70 percent. If it goes well, we are targeting it to finish by the end of March," he conveyed, Saturday (3/27).

PPSU Personnel Repair Drainage Cover on Jalan Duren Tiga

According to him, mud dredging work is carried out as deep as 30-100 centimeters. His side deployed 7 SDA Unit personnel and 1 excavator to dredge mud from the channel.

"Channel needs to be cleaned because the silt already dense thus it can't hold much water. After dredging, we hope it can increase its capacity," he stated.

Linked News
Popular News indeks
  1. Deputy Gov Rano: Meat Stocks Secured Up to Ramadhan

    access_time22-02-2025 remove_red_eye544 personBudhi Firmansyah Surapati
  2. Jakarta to Hold Cheap Food Bazaar at 193 Locations

    access_time22-02-2025 remove_red_eye439 personBudhi Firmansyah Surapati
  3. Pramono - Rano Expected to Realize Better Resident Welfare

    access_time20-02-2025 remove_red_eye309 personBudhi Firmansyah Surapati
  4. Jakartans Invited to Participate in HPSN 2025 Event

    access_time21-02-2025 remove_red_eye298 personAldi Geri Lumban Tobing
  5. Jakarta Commits to Realizing National Waste Management Pilot Project

    access_time17-02-2025 remove_red_eye294 personFolmer