Repair of Kali Gongseng River Bridge Has Reached 70 Percent

The Kali Gongseng River Bridge repair work in the border area of RW 06 and 07, Cijantung Urban Village, Pasar Rebo, East Jakarta has touched 70 percent.

It is targeted to be complete for two weeks ahead,"

East Jakarta Bina Marga Sub-agency's Road and Bridge Division Head, Ilham Raya expressed the bridge as long as 8 meters and 3.5 meters width was under repair, as the position was very low. As a result, a lot of garbage was stuck in the bridge when heavy rain poured and caused inundation in the residential area. The bridge was seen being demolished and rebuilt higher than before.

"To conduct it, eight personnel have been deployed to install the bridge's floor plate (habim iron) and bordes plate. The bridge frame made of iron has also been neatly installed," he said.

18 Bridges Beautified in Menteng and Cempaka Putih

He ensured that there were no technical problems in the field, but only access to its location which was narrow and winding.

"It is targeted to be complete for two weeks ahead," he stated.

Linked News
Popular News indeks
  1. City Council Strengthens Synergy with Central Legislators to Support Jakarta`s Development

    access_time30-07-2026 remove_red_eye1076 personFakhrizal Fakhri
  2. Jakarta Partners with Five Satellite Cities for Greater Jakarta Connected Initiative

    access_time30-07-2026 remove_red_eye602 personBudhi Firmansyah Surapati
  3. Pramono Praises Young Innovators at the Jakarta Robotic Games 2026

    access_time28-07-2026 remove_red_eye488 personDessy Suciati
  4. Jakarta Reaffirms Commitment to Preserving Cultural Heritage

    access_time31-07-2026 remove_red_eye486 personDessy Suciati
  5. Various Events Prepared for Jakarta`s 5th Century Anniversary

    access_time29-07-2026 remove_red_eye472 personFakhrizal Fakhri