Lancang Island Barrier Embankment Strengthened to Anticipate Abrasion
access_time June 07 2021 10:28 PM remove_red_eye 808
Reported by Suparni | Translated by Nugroho Adibrata
Reported by Suparni | Translated by Nugroho Adibrata
So far the project work has touched 37 meters
The Thousand Islands Water Resources (SDA) Sub-agency installs a bronjong (rocks wrapped in plaited wires) to strengthen the Lancang Island barrier embankment in RT 01/01, Pari Island Urban Village, South Thousand Islands Sub-district.
Thousand Islands SDA Sub-agency Head, Hendri disclosed the embankment as long as 87 meters length was in the front of the Sea Water Reverse Osmosis (SWRO) building.
Breakwater Repair Work on East Side of Karya Island Has Reached 80 Percent"So far the project work has touched 37 meters," he expressed, Monday (6/7).
To conduct it, he deployed 19 personnel to the location. It was targeted to be complete in the forthcoming July.
"Bronjong is also installed to anticipate abrasion due to high waves," he stated.