Breakwater Repair Work on East Side of Karya Island Has Reached 80 Percent
Reported by Suparni | Translated by Nugroho Adibrata
Our target is in two days ahead. Hopefully it can protect the Karya Island from abrasion and high waves
The Thousand Islands Water Resources (SDA) Sub-agency is seen repairing the damaged breakwater on the east side of Karya Island, Panggang Island Urban Village, North Thousand Islands Sub-district. Currently the progress has reached 80 percent.
Thousand Islands SDA Sub-agency Head, Hendri said the repairs carried out by the officers included rearranging the massive cube that collapsed due to the brunt of the high waves some time ago. Then the massive cube was tied with alternating wire to make it strong and sturdy.
Untung Jawa Island Breakwaters are Being under Maintenance"The repair that takes 210 meters long has been conducted since early June," he expressed, Friday (6/4).
To conduct it, his side had deployed as many as 10 personnel to the location.
"Our target is in two days ahead. Hopefully it can protect the Karya Island from abrasion and high waves," he stated.