Pembangunan Saluran Air di Jl Ksatriaan 8 Kebon Manggis Capai 70 Persen

Progress of Channel Construction on Jl. Ksatriaan 8 Kebon Manggis Reaches 70 Percent

Construction of 729-meter water channel located in Komplek TNI AD, on Jl. Ksatriaan 8 RW 03, Kebon Manggis, Matraman, East Jakarta has touched 70 percent.

Currently, the work progress has reached around 70 percent and targeted to be completed in November

East Jakarta SDA Sub-agency's Drainage Development and Construction Section Head, Tengku Saugi Zikri stated, his side deployed one mini backhoe to accelerate the construction work.

"Total length of this channel is 729 meters. Currently, the work progress has reached around 70 percent and targeted to be completed in November," he explained, Friday (10/1).

Starting October 3, Traffic Engineering on Jl. I Gusti Ngurah Rai will Be Implemented

According to him, this water channel will use U-ditch concrete with size 60x60 centimeters, 80x80 centimeters, and box culvert with size 80x80 centimeters.

The construction work was started from in front of church to Ksatriaan connecting (Phb) channel.

"We hope this construction work can be completed on schedule, which is 75 days," he closed.

Linked News
Popular News indeks
  1. Jakarta Administration Steps Up Proactive Fire Prevention Efforts

    access_time09-10-2026 remove_red_eye502 personDessy Suciati
  2. Kramat Pulo Fire Survivors Get Help Replacing School Documents

    access_time09-10-2026 remove_red_eye480 personFolmer
  3. New Kelapa Gading-Pulogadung Road to Ease Traffic and Improve Access

    access_time10-10-2026 remove_red_eye475 personAldi Geri Lumban Tobing
  4. Basic Supplies Distributed to Pinang Ranti Fire Survivors

    access_time09-10-2026 remove_red_eye464 personNurito
  5. North Jakarta PPAPP Promotes SIDAYA to Improve Seniors' Quality of Life

    access_time09-10-2026 remove_red_eye459 personAnita Karyati