Collapsed Sheet Pile on Jalan Kramat Kwitang Nomor 9 Being Repaired

Some 20 officers and excavators from Central Jakarta Water Resources (SDA) Sub-agency has started repairing the collapsed sheet pile of the water channel on Jalan Kramat Kwitang Number 9, Kwitang Urban Village, Senen Sub-district.

Thus far it has touched 40 percent and is targeted to be complete next week

Central Jakarta SDA's Maintenance Division Head, Achmad Daeroby said, the sheet pile was collapsed after being hit by a landslide due to the theft of underground cables by irresponsible people.

"Indeed a lot of utility cables under these sidewalks and channels. We fixed it by reinstalling the u-ditch," he expressed, Tuesday (10/12).

Collapsed Sheet Pile in Rawa Baboon Ciracas Being Repaired

According to him, it was carried out by installing a u-ditch measuring 80 centimeters long, 60 centimeters wide and 120 centimeters high. It was also elevated around 1.15 meters high.

"Thus far it has touched 40 percent and is targeted to be complete next week," he stated.

Linked News
Popular News indeks
  1. Rano: CIEIE 2026 to Catapult Jakarta’s MSMEs onto the International Stage

    access_time25-08-2026 remove_red_eye758 personBudhi Firmansyah Surapati
  2. Jakarta Deploys 120 Personnel to Counteract Traffic Disruption for Today’s Protests

    access_time27-08-2026 remove_red_eye741 personAldi Geri Lumban Tobing
  3. Pramono Pushes for Partnership Between New Toto Tentrem and Tarakan Hospitals

    access_time24-08-2026 remove_red_eye669 personDessy Suciati
  4. Transjakarta Commits to Transport Equality Across the Seribu Islands

    access_time24-08-2026 remove_red_eye640 personAldi Geri Lumban Tobing
  5. Transjakarta Resumes Operations with Strategic Service Adjustments

    access_time28-08-2026 remove_red_eye620 personAldi Geri Lumban Tobing