photo TP Moan Simanjuntak - Beritajakarta.id

Channel Construction in Srengseng Urban Forest Reaches 30 Percent

Progress of 400-meter channel construction work in Srengseng Urban Forest Area (KHK), West Jakarta, which has been started since November 17, 2021 has now reached 30 percent. This project is targeted to be completed in April 2022.

The work has been carried out by 14 SDA Unit personnel since November 17, 2021

West Jakarta Water Resources (SDA) Sub-agency's Maintenance Section Coordinator, Lukman Hariadi mentioned that channel will be built with height of 2 meters and upper width of 150 centimeters. Later on, channels from residential areas will be connected with this channel and flow to Srengseng Urban Forest Reservoir.

"The work has been carried out by 14 SDA Unit personnel since November 17, 2021," he stated, Tuesday (1/11).

Koja SDA Unit Elevates Retaining Wall on Jalan Lorong 103

Channel construction was expected to overcome inundation that often occurs in the surrounding area during rainy season.

"Currently the progress has reached about more than 30 percent. If it goes well, it will be finished around April 2022," he explained.

Linked News
Popular News indeks
  1. Commission D Legislator Supports Park Monitoring Optimization

    access_time20-01-2025 remove_red_eye1519 personDessy Suciati
  2. Realizing Food Self-Sufficiency, Jakarta Holds Simultaneous Planting Activity

    access_time21-01-2025 remove_red_eye941 personAldi Geri Lumban Tobing
  3. Gulkarmat to Intensify Fire Mitigation Education

    access_time22-01-2025 remove_red_eye449 personBudhi Firmansyah Surapati
  4. BMKG Warns of Potential High Rainfall in Jakarta

    access_time22-01-2025 remove_red_eye423 personDessy Suciati
  5. City and Kejati Forge Cooperation for Good Government Governance

    access_time21-01-2025 remove_red_eye412 personFolmer