Channel Construction in Srengseng Urban Forest Reaches 30 Percent
Reported by TP Moan Simanjuntak | Translated by Maria Inggita
Progress of 400-meter channel construction work in Srengseng Urban Forest Area (KHK), West Jakarta, which has been started since November 17, 2021 has now reached 30 percent. This project is targeted to be completed in April 2022.
The work has been carried out by 14 SDA Unit personnel since November 17, 2021
West Jakarta Water Resources (SDA) Sub-agency's Maintenance Section Coordinator, Lukman Hariadi mentioned that channel will be built with height of 2 meters and upper width of 150 centimeters. Later on
, channels from residential areas will be connected with this channel and flow to Srengseng Urban Forest Reservoir."The work has been carried out by 14 SDA Unit personnel since November 17, 2021," he stated, Tuesday (1/11).
Koja SDA Unit Elevates Retaining Wall on Jalan Lorong 103Channel construction was expected to overcome inundation that often occurs in the surrounding area during rainy season.
"Currently the progress has reached about more than 30 percent. If it goes well, it will be finished around April 2022," he explained.