Progress of Ciliwung River Dredging Work in Kebon Melati Touches 80 Percent

The dredging work on Ciliwung River West Flood Canal (KBB) on Jalan Tenaga Listrik, Kebon Melati, Tanah Abang, Central Jakarta has reached 80 percent.

We are targeting to complete it this year

Central Jakarta SDA Sub-agency's Maintenance Section Head, Achmad Daeroby stated, dredging has been carried out since March 2011, from Jalan Pintu Air Karet until Jalan K.S. Tubun along 1,047 meters.

"We are targeting to complete it this year," he mentioned, Thursday (3/3).

South Jakarta SDA Optimizes Reservoirs and Rivers Dredging

It was carried out with a depth of 1.5 meters. It was estimated around 55,282 cubic meters of mud would be dredged from the site.

"Every day, we dredge and transport 44,062 cubic meters of mud," he added.

His side deployed 20 personnel and 3 amphibious excavators,  1 long arm excavator, and 10 dump trucks for dredging the Ciliwung River.

"We expect it can increase the river's capacity and can be completed on time," he said.

Linked News
Popular News indeks
  1. Central Jakarta Administration Acts Swiftly to Handle Kebon Kosong Fire

    access_time02-06-2026 remove_red_eye1407 personFolmer
  2. North Jakarta KPKP Ensures Sacrificial Meat is Safe for Consumption

    access_time27-05-2026 remove_red_eye881 personAnita Karyati
  3. Jakarta Waives Motor Vehicle Tax Fines and Title Transfer Fees

    access_time01-06-2026 remove_red_eye846 personAldi Geri Lumban Tobing
  4. Dharma Jaya Supports Jakarta PWNU Qurban Program

    access_time27-05-2026 remove_red_eye745 personAldi Geri Lumban Tobing
  5. Commemorating Vesak, Jakarta Lights Up with Illumination of Jakarta 2026

    access_time30-05-2026 remove_red_eye646 personBudhi Firmansyah Surapati