Pengerukan Kali Grogol Segmen Susilo Capai 99 Persen

Grogol River Dredging on Susilo Segment Touches 99 Percent

The West Jakarta Water Resources (SDA) Sub-agency continues to accelerate dredging work on the Segment II Susilo of Grogol River, Jalan Latumenten, Grogol, Grogol Petamburan.

It is carried out to increase the river's capacity

The progress of river dredging work which began on February 20, 2020, has now reached 99 percent.

West Jakarta SDA Sub-agency Head, Purwanti stated, her side used heavy equipment to dredge mud on Grogol River with a depth of 2 meters.

Jakarta Doesn't Appeal to Administrative Court Decision Regarding Flood Handling

"It is carried out to increase the river's capacity," she mentioned, Friday (3/11).

As a result, her side could transport mud to 10 dump trucks a day. Later on, dredging on the river would be continued to the Borobudur Pump area.

"Hopefully, the Grogol area will be free from inundation after the dredging," she conveyed.

Linked News
Popular News indeks
  1. 21 Parking Spots to Make Your Jakarta 499th Anniversary Experience Seamless

    access_time26-06-2026 remove_red_eye911 personAldi Geri Lumban Tobing
  2. Over 11 Kilometers of Overhead Utility Cables Removed in West Jakarta

    access_time26-06-2026 remove_red_eye873 personBudhi Firmansyah Surapati
  3. Celebrating Jakarta`s 499th Anniversary at HI, Please Use Public Transportation

    access_time26-06-2026 remove_red_eye737 personAldi Geri Lumban Tobing
  4. 190 Satpol PP Personnel Deployed to Secure Jakarta Anniversary Celebration

    access_time26-06-2026 remove_red_eye701 personFolmer
  5. Night at The Library Marks Jakarta's 499th Anniversary with Five-Century Message

    access_time27-06-2026 remove_red_eye677 personAnita Karyati