Pengerukan Kali Grogol Segmen Susilo Capai 99 Persen

Grogol River Dredging on Susilo Segment Touches 99 Percent

The West Jakarta Water Resources (SDA) Sub-agency continues to accelerate dredging work on the Segment II Susilo of Grogol River, Jalan Latumenten, Grogol, Grogol Petamburan.

It is carried out to increase the river's capacity

The progress of river dredging work which began on February 20, 2020, has now reached 99 percent.

West Jakarta SDA Sub-agency Head, Purwanti stated, her side used heavy equipment to dredge mud on Grogol River with a depth of 2 meters.

Jakarta Doesn't Appeal to Administrative Court Decision Regarding Flood Handling

"It is carried out to increase the river's capacity," she mentioned, Friday (3/11).

As a result, her side could transport mud to 10 dump trucks a day. Later on, dredging on the river would be continued to the Borobudur Pump area.

"Hopefully, the Grogol area will be free from inundation after the dredging," she conveyed.

Linked News
Popular News indeks
  1. Hosted in Sydney, Pramono Discusses Opening Australian Campuses in Jakarta

    access_time25-11-2026 remove_red_eye822 personDessy Suciati
  2. Transjakarta Extends Operating Hours for MCR Concert at JIS

    access_time22-11-2026 remove_red_eye668 personAldi Geri Lumban Tobing
  3. Pasar Baru Festival 2026 Brings Historic District to Life

    access_time27-11-2026 remove_red_eye508 personFolmer
  4. Meet Boan, A Retired Teacher Crafting Traditional Betawi Masks

    access_time22-11-2026 remove_red_eye491 personNurito
  5. Jakarta Tops Teqball at 2026 PON Beach Games

    access_time27-11-2026 remove_red_eye446 personAldi Geri Lumban Tobing