Pengerukan Kali Ciliwung BKB Capai 79,70 Persen
....
photo Anita Karyati - Beritajakarta.id

Progress of Ciliwung River Dredging Work in Kebon Melati Touches 80 Percent

The dredging work on Ciliwung River West Flood Canal (KBB) on Jalan Tenaga Listrik, Kebon Melati, Tanah Abang, Central Jakarta has reached 80 percent.

We are targeting to complete it this year

Central Jakarta SDA Sub-agency's Maintenance Section Head, Achmad Daeroby stated, dredging has been carried out since March 2011, from Jalan Pintu Air Karet until Jalan K.S. Tubun along 1,047 meters.

"We are targeting to complete it this year," he mentioned, Thursday (3/3).

South Jakarta SDA Optimizes Reservoirs and Rivers Dredging

It was carried out with a depth of 1.5 meters. It was estimated around 55,282 cubic meters of mud would be dredged from the site.

"Every day, we dredge and transport 44,062 cubic meters of mud," he added.

His side deployed 20 personnel and 3 amphibious excavators,  1 long arm excavator, and 10 dump trucks for dredging the Ciliwung River.

"We expect it can increase the river's capacity and can be completed on time," he said.

Linked News
Popular News indeks
  1. Takjil Supervision in Central Jakarta Begins Second Week

    access_time02-03-2025 remove_red_eye473 personBudhi Firmansyah Surapati
  2. Dishub: Lay Bay Remains Optimal to Support Public Transportation User Comfort

    access_time02-03-2025 remove_red_eye406 personAldi Geri Lumban Tobing
  3. Traffic Diverted on Jalan Jatinegara Barat as Floods Hit Jakarta

    access_time04-03-2025 remove_red_eye377 personNurito
  4. Job Fair at Pluit Junction Mall Offers 1,500 Vacancies

    access_time05-03-2025 remove_red_eye272 personAnita Karyati
  5. City Government Assists Flood Survivors in East Jakarta

    access_time03-03-2025 remove_red_eye268 personNurito

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik