Pembangunan JIS Ditarget Rampung Awal April 2022
....
photo Istimewa - Beritajakarta.id

JIS Construction is Targeted for Completion in Early April 2022

The construction of Jakarta International Stadium (JIS) which is located on Jalan RE Martadinata, Papanggo, Tanjung Priok, North Jakarta is targeted to be completed in early April 2022.

It is still according to the initial plan, both in terms of time and cost

Currently, the construction progress has reached 98.26 percent. Most of the work is already in the completion stages, including retractable roof, landscaping, and finishing.

"Technically, there are no significant obstacles. It is still according to the initial plan, both in terms of time and cost," said Nadia Diposanjoyo, Division Head of PT Jakarta Propertindo (Jakpro) Corporate Secretary and Public Relation, on Tuesday (3/15).

Transjakarta Tests Non-BRT Services for JIS - Senen Route

According to her, JIS Soft Launching which was planned to be enlivened by the Youth Championship (IYC) was delayed due to the COVID-19 pandemic. However, Jakpro would make an effort to make it come true soon.

"However, we'll coordinate with the Jakarta Government first to make it come true," she added.

Apart from being used for football matches, the JIS which was designed as the sportainment stadium with FIFA and Platinum Level Green Building certifications were also equipped with various facilities.

Those facilities were provided to support musical performance and other world-class entertainment activities with excellent lighting and sound systems.

Jakpro is currently promoting a public visit program, #YukKitaKeJIS, with the government to introduce JIS features and facilities to the public.

Linked News
Popular News indeks
  1. W. Jakarta Bina Marga Sub-agency Repairs Kembangan Outer Ring Road Section

    access_time07-05-2024 remove_red_eye408 personTP Moan Simanjuntak
  2. Jakarta Takes Part in Arabian Travel Market 2024 in Dubai

    access_time08-05-2024 remove_red_eye326 personAldi Geri Lumban Tobing
  3. Three Boats Catch Fire in Muara Baru, No Casualties

    access_time06-05-2024 remove_red_eye315 personAnita Karyati
  4. Tengah Urban Village PPSU Personnel Clean Fire Debris

    access_time10-05-2024 remove_red_eye299 personNurito
  5. Jalan YRS III Repairs in South Jakarta Completed

    access_time10-05-2024 remove_red_eye291 personTiyo Surya Sakti