Pembangunan Embung Penganten Ali Capai Lima Persen

Construction of Penganten Ali Embung in Ciracas Keeps Being Accelerated

Embung is dredged up to four meters deep using three heavy equipment

The Penganten Ali Embung (artificial lake) construction in Ciracas Urban Village, East Jakarta keeps being accelerated. Its construction has been carried out since early August and is targeted for completion by the end of this year.

Thus far, the work progress is only about five percent.

East Jakarta to Build Embung in Cibubur to Anticipate Flooding

Maintenance Division Head Puryanto expressed that the embung, which is built on a 9,300-square-meter land was to cope with the overflow of the Cipinang River which usually inundates RW 06, Ciracas Urban Village.

"Embung is dredged up to four meters deep using three heavy equipment, consisting of two long-arm excavators and one standard excavator," he explained, Monday (9/5).

If it was done, the surrounding area would be used as a vehicle for ecotourism with a 5-meter-wide jogging track facility

"People will feel safe and comfortable when exercising while traveling in these locations," he explained.

 East Jakarta Mayor, Muhammad Anwar hoped that the Penganten Ali Embung could accommodate approximately 75,000 cubic meters of water, which is a flood controller in RW 06 Ciracas area.

"It is also designed as a tourist destination. That's why we prepare a jogging track at the location, including an interactive park and an outdoor theater," he concluded.

Linked News
Popular News indeks
  1. Water Channel on Jalan SPG 7 Being Improved

    access_time18-09-2026 remove_red_eye828 personNurito
  2. Jakarta Govt Fully Backs Kanye West's Ye Live in Jakarta 2026

    access_time16-09-2026 remove_red_eye731 personDessy Suciati
  3. Jakarta Pushes to Strengthen Food Ecosystem

    access_time18-09-2026 remove_red_eye601 personAldi Geri Lumban Tobing
  4. Pramono Departs for New York to Discuss Climate and Food Crises

    access_time18-09-2026 remove_red_eye545 personDessy Suciati
  5. Operations of the MV Doulos Hope Ship Library Delayed

    access_time18-09-2026 remove_red_eye537 personAnita Karyati