This Week, Sheet Pile Repairs in Semper Barat Residential Completed
Reported by Budhi Firmansyah Surapati | Translated by Nugroho Adibrata
Repairs to the channel in the residential area on Jalan GG 2, Block X, RT 04/12, Semper Barat Urban Village carried out by the Cilincing Sub-district Water Resources (SDA) Executing Unit since July 11 is targeted to be completed this week.
Hopefully, it can be done on the target
Cilincing Sub-district SDA Executing Unit Head, Cahyo Budi Setiawan expressed the repair was done to follow up on residents' aspirations through Musrenbang forum.
"Some of the sheet pile had collapsed and we rebuild it. Afterwards, we will attach a manhole cover at the top of the channel," he expressed, Wednesday (8/9).
SDA Agency Builds New Sheet Pile in Munjul Reservoir AreaHe explained the repaired section of channel is about 117 meters long and 60 centimeters wide with about 90 centimeters deep.
"We send eight personnel to the location every day. The work progress has touched 90 percent. It is targeted to be completed this week," he asserted.
RW 12 Semper Barat Urban Village Head, Tarkim appreciated the repair action and hoped that it could be completed before the rainy season.
"Hopefully, it can be done on the target," he hoped.