You don't have javascript enabled. Good luck with that.
Pencarian
352 Kubik Lumpur Telah Diangkut Dari Pengerukan Kali Pesanggrahan

352 Cubic Meters of Mud Transported from Pesanggrahan River

The West Jakarta Water Resources (SDA) Sub-agency is dredging the 389-meter-long Pesanggrahan River mud that crosses Meruya Utara Urban Village in Kembangan Sub-district and Kebon Jeruk Urban Village in Kebon Jeruk Sub-district.

As the initial stage, we deployed two excavators and four trucks to transport the mud

West Jakarta SDA Sub-agency Head, Purwanti expressed the work which has been running for four days has succeeded in transporting as much as 352 cubic feet of mud.

"As the initial stage, we deployed two excavators and four trucks to transport the mud," she expressed, Tuesday (8/15).

Pesanggrahan River in Kebon Jeruk will Soon Be Dredged from Mud

According to her, the dredging was done from 3.5 to four meters deep. To speed up it, next week, her party would add two amphibious excavators and a truck to transport mud.

"It is carried out, thus the river capacity becomes more and the water flow can flow smoothly, thus it is expected to minimize inundation during the rainy season," she uttered.

It is targeted for the completion until six months ago.

Linked News
Popular News indeks
  1. Fire at Pondok Bambu Allegedly Triggered by Electrical Short

    access_time19-05-2026 remove_red_eye1390 personNurito
  2. Governor Pramono Named Vice Chair of C40 Cities Steering Committee

    access_time18-05-2026 remove_red_eye1022 personAldi Geri Lumban Tobing
  3. Kultura Market in Pademangan Barat Attracts Crowds

    access_time22-05-2026 remove_red_eye891 personAnita Karyati
  4. Inundation on DI Panjaitan Road Recede

    access_time20-05-2026 remove_red_eye849 personNurito
  5. Dharma Jaya Ready for Thousands of Eid al-Adha Sacrifices

    access_time20-05-2026 remove_red_eye664 personAldi Geri Lumban Tobing