352 Cubic Meters of Mud Transported from Pesanggrahan River

The West Jakarta Water Resources (SDA) Sub-agency is dredging the 389-meter-long Pesanggrahan River mud that crosses Meruya Utara Urban Village in Kembangan Sub-district and Kebon Jeruk Urban Village in Kebon Jeruk Sub-district.

As the initial stage, we deployed two excavators and four trucks to transport the mud

West Jakarta SDA Sub-agency Head, Purwanti expressed the work which has been running for four days has succeeded in transporting as much as 352 cubic feet of mud.

"As the initial stage, we deployed two excavators and four trucks to transport the mud," she expressed, Tuesday (8/15).

Pesanggrahan River in Kebon Jeruk will Soon Be Dredged from Mud

According to her, the dredging was done from 3.5 to four meters deep. To speed up it, next week, her party would add two amphibious excavators and a truck to transport mud.

"It is carried out, thus the river capacity becomes more and the water flow can flow smoothly, thus it is expected to minimize inundation during the rainy season," she uttered.

It is targeted for the completion until six months ago.

Linked News
Popular News indeks
  1. Nighttime Surveillance on Railroad Banks of Jalan I Gusti Ngurah Rai Intensified

    access_time08-05-2026 remove_red_eye2625 personNurito
  2. Closure of Railway Level Crossings Socialized

    access_time13-05-2026 remove_red_eye2032 personTiyo Surya Sakti
  3. Governor Pram Appreciates Residents for Keeping Jakarta Safe and Comfortable

    access_time09-05-2026 remove_red_eye963 personFolmer
  4. Waste Sorting Movement Boosts Circular Economy

    access_time12-05-2026 remove_red_eye825 personFakhrizal Fakhri
  5. Fire Burns Five Houses in Cengkareng Extinguished

    access_time12-05-2026 remove_red_eye728 personBudhi Firmansyah Surapati