Pengurasan Saluran Jalan VIJ II Capai 60 Persen

Channel on Jalan VIJ II Cideng Being Dredged from Mud

The Central Jakarta Water Resources (SDA) Sub-agency dredges the mud from the water channel on Jalan VIJ II, RW 06, Cideng, Gambir.

The progress work has touched 60 percent

Gambir Sub-district SDA Executing Unit Head, Imawan expressed the dredging was carried out to follow up on residents' aspirations in the Musrenbang 2023.

"It has been realized since August 20 and is targeted for completion by the end of September 2023," he expressed, Sunday (9/3).

Connecting Channel at Gang BO Being Dredged

He explained the mud thickness had reached 20 centimeters. The length of the drained channel was 1,424 meters with 60 centimeters wide.

"The progress work has touched 60 percent," he said.

It involved 17 personnel. Besides draining, they were also making six drainage tranks in the size of 60x60 centimeters along the channel.

"It aims to accommodate water maximally to anticipate inundation when it rains," he stated.

Linked News
Popular News indeks
  1. Jakarta Administration Steps Up Proactive Fire Prevention Efforts

    access_time09-10-2026 remove_red_eye527 personDessy Suciati
  2. New Kelapa Gading-Pulogadung Road to Ease Traffic and Improve Access

    access_time10-10-2026 remove_red_eye515 personAldi Geri Lumban Tobing
  3. MRT Jakarta Integrates Ticket Payments with JakLingko from October 12

    access_time10-10-2026 remove_red_eye499 personAldi Geri Lumban Tobing
  4. Kramat Pulo Fire Survivors Get Help Replacing School Documents

    access_time09-10-2026 remove_red_eye496 personFolmer
  5. Basic Supplies Distributed to Pinang Ranti Fire Survivors

    access_time09-10-2026 remove_red_eye493 personNurito