Pengurasan Saluran Jalan VIJ II Capai 60 Persen

Channel on Jalan VIJ II Cideng Being Dredged from Mud

The Central Jakarta Water Resources (SDA) Sub-agency dredges the mud from the water channel on Jalan VIJ II, RW 06, Cideng, Gambir.

The progress work has touched 60 percent

Gambir Sub-district SDA Executing Unit Head, Imawan expressed the dredging was carried out to follow up on residents' aspirations in the Musrenbang 2023.

"It has been realized since August 20 and is targeted for completion by the end of September 2023," he expressed, Sunday (9/3).

Connecting Channel at Gang BO Being Dredged

He explained the mud thickness had reached 20 centimeters. The length of the drained channel was 1,424 meters with 60 centimeters wide.

"The progress work has touched 60 percent," he said.

It involved 17 personnel. Besides draining, they were also making six drainage tranks in the size of 60x60 centimeters along the channel.

"It aims to accommodate water maximally to anticipate inundation when it rains," he stated.

Linked News
Popular News indeks
  1. City Council Strengthens Synergy with Central Legislators to Support Jakarta`s Development

    access_time30-07-2026 remove_red_eye1045 personFakhrizal Fakhri
  2. Jakarta Government Prepares Rp 249 B to Renovate Four Schools

    access_time25-07-2026 remove_red_eye880 personDessy Suciati
  3. Rano Urges Jakarta Scouts to Be Active in Waste Sorting Movement

    access_time25-07-2026 remove_red_eye698 personAldi Geri Lumban Tobing
  4. Pramono Encourages Residents to Stay Active at Rasuna Said CFD

    access_time26-07-2026 remove_red_eye628 personFolmer
  5. Jakarta Steps Up Food Waste Prevention

    access_time25-07-2026 remove_red_eye581 personAldi Geri Lumban Tobing