You don't have javascript enabled. Good luck with that.
Pencarian
Dishub Rekayasa Lalin Sejumlah Jalan di Kebayoran Baru dan Setiabudi
....
photo Ilustrasi - Beritajakarta.id

Traffic Diversion Implemented in Kebayoran Baru and Setiabudi

The Jakarta Transportation Agency (Dishub) diverts traffic on several roads of Setiabudi and Kebayoran Baru sub-districts as the city administration develops the Drainage System Management and Development conducted by the South Jakarta Water Resources Sub-agency (SDA).

This work is in Setiabudi and Kebayoran Baru sub-districts

"This work is in Setiabudi and Kebayoran Baru sub-districts," expressed Jakarta Dishub Head, Syafrin Liputo, Thursday (6/5).

According to him, traffic diversion would be implemented according to the stages of work.

PPSU Personnel of Cibubur Construct 10 Reservoir Wells

Here are details of traffic diversion during the work:

1) Jalan Prof DR Satrio

a. Work location for box culvert measuring 200x200 centimeters at the intersection of Jalan Prof DR Satrio and Jalan Tiong in front of the Amurva Bhumi Vihara

b. Work stages are divided into five segments and conducted in stages

c. During work on segment 3, the West-West turn to the West side is approximately 10 meters from the existing U-turn

d. To reduce traffic density, road users from East/Tebet to West/Tanah Abang can take Jalan Denpasar - Jalan Setiabudi - Jalan Setiabudi Utara - Jalan Setiabudi Tengah - Jalan Galunggung - etc

e. Work implementation time is from May 27 to August 30, 2024

2) Jalan Minangkabau

a. Work location for box culvert measuring 100x100 centimeters at the intersection of Jalan Minangkabau Barat Raya and Jalan Kota Gedang

b. Work stages are divided into four segments and conducted in stages

c. There will be a narrowing/reduction of traffic lanes along the work area, Jalan Kota Gedang will have an open and close traffic system, there will be a reduction of one lane on Jalan Minangkabau Barat

d. Work implementation time is from June 3 to June 18, 2024

3) Jalan Denpasar Raya on the South side of the Channel IV AS Box Culvert measuring 100x100 centimeters, along 478 meters

a.Work is conducted in stages with the length of the work area ranging from 25 to 50 meters (depending on road conditions) for each excavation with six meters wide

b. There will be a narrowing/reduction of traffic lanes throughout the work area

c. There will be demolition of the median dividing the road during the work on Jalan Denpasar to adjust road lanes

d. Crossing work at Jalan Gilimanuk - Jalan Denpasar Raya intersection is divided into two segments after the work on Jalan Denpasar is completed. The work time is from May 13 to 25 August, 2024

4) Jalan Denpasar Raya on the North side of Channel lV A U-Ditch measuring 100x100cm and Box Culvert measuring 100x100 centimeters with 239 meters long

a. Work is conducted in stages with a work area length of 20 meters (adjusting to road conditions) each excavation is 3.5 meters wide

b. There will be a narrowing/reduction of traffic lanes throughout the work area

c. Work time is from August 12 to October 13, 2024

5) Jalan Denpasar Selatan on the North side and South side of Channel lll A U-Ditch measuring 100x100 centimeters and Box Culvert measuring 100x100 centimeters

a. Work is conducted in stages with a work area length of 20 meters (adjusting to road conditions) for each excavation with a width of 1.5 meters and 2 meters

b. There will be a narrowing/reduction of traffic lanes throughout the work area

c. Work time is July 22 to September 1, 2024 (North side) with a length of 1,60 meters and June 17 to July 21, 2024 (South side) with a length of 169 meters

6) Jalan Taman Patra XV and Jalan Patra Terusan

a. Work for the length of the box culvert 434 measures 150x150 centimeters

b. Work is conducted in stages with a work area length of 50 meters (adjusting to road conditions) for each excavation with a width of 3.5 meters

c. There will be a narrowing/reduction of traffic lanes throughout the work area

d. Jalan Taman Patra Channel crossing work is divided into two segments in stages

e. Work time is from May 13 to September 29, 2024

7) Jalan Jendral Gatot Subroto Channel I U-Ditch 800x800 with a length of 210 meters

a. Work is on the sidewalk with work stages every 50 meters

b. Work time is May 13 to June 16, 2024

8) Jalan HR Rasuna Said, Channel V U-Ditch measuring 100x100 centimeters and Box Culvert measuring 100x100 centimeters

a. Work is conducted in stages with the length of the work area ranging from 29 to 50 meters (depending on road conditions) for each excavation with a width of 3.5 meters on the slow lane

b. There will be a narrowing/reduction of traffic lanes throughout the work area

c. Work implementation time is from June 17 to September 18, 2024

9) Jalan Nipah Xii (manual jacking and open-cut work)

a. Work will close Jalan Nipah Xll on the East side during the work

b. Residents around Jalan Nipah can still use Jalan Nipah Xll on the West side - Jalan Nipah Raya to get to and from Jalan Prapanca

c. Work time: May 20 to August 18, 2024 (AP5, SP6, SP7, AP8, and Downstream), June 20 to August 18, 2024 (AP4)

10) Jalan Nipah Raya crossing ke Jalan Prapanca Raya

a. Work will close Jalan Nipah Raya (crossing Jalan Prapanca)

b. Residents around Jalan Nipah can still use Jalan Nipah Xll - Jalan Nipah Raya - Jalan Nipah Xll - Jalan Kintamani - Jalan Prapanca to get to and from Jalan Prapanca

c. Work time: June 24 to November 24, 2024 (AP3), August 19 to November 24, 2024 (SP2, AP1 and Downstream)

"I call on road users to avoid the roads and follow the traffic diversion," he stated.

Linked News
Popular News indeks
  1. Free Additional Nutritious Food Distributed to 31 Toddlers in Kalibata

    access_time13-09-2024 remove_red_eye1146 personTiyo Surya Sakti
  2. Jakarta Women's Football Team Ready to Face West Java at PON XXI Final

    access_time13-09-2024 remove_red_eye843 personFolmer
  3. Water Channel Dredging on Bendungan Melayu Reaches 50 Percent

    access_time18-09-2024 remove_red_eye819 personAnita Karyati
  4. Jakarta Leads Medal Standing at PON XXI

    access_time17-09-2024 remove_red_eye772 personFolmer
  5. PON XXI Temporary Standings: Jakarta Continues to Shadow East Java

    access_time13-09-2024 remove_red_eye751 personAldi Geri Lumban Tobing