July, Channels Normalization on Jalan Kampung Bali XX Completed

The Central Jakarta Water Resources Sub-agency (SDA) is normalizing channels that have experienced damage on Jalan Kampung Bali XX, RT 03/07, Kampung Bali Urban Village, Tanah Abang.

Every day, we deploy 10 personnel for this work

It has been ongoing since Monday (6/24) and ia targeted to be completed in mid-July 2024.

March, Channel Normalization on Jalan Kramat Kwitang Done

Tanah Abang Sub-district SDA Executing Unit Head, Eli Menawan Sari said the normalization was done, because the channel was badly damaged and collapsed and blocked the water flow.

"That's why, we reshaped the alignment and installed a concrete U-ditch," he expressed, Wednesday (6/26).

The normalization conducted included replacing the channel material which previously used new construction with a U-ditch measuring 60x60 centimeters.

"Every day, we deploy 10 personnel for this work. The target is to complete it in three weeks or by mid-July," he asserted.

The work received appeciation from one of the residents in RW 07 Kampung Bali. He hoped, it could accommodate water optimally.

"If we use U-ditch, it will last longer. Hope it can be completed quickly," he stated.

Linked News
Popular News indeks
  1. Hosted in Sydney, Pramono Discusses Opening Australian Campuses in Jakarta

    access_time25-11-2026 remove_red_eye720 personDessy Suciati
  2. Pramono Pushes to Complete Long-Delayed Pluit JLNT by March 2027

    access_time20-11-2026 remove_red_eye718 personDessy Suciati
  3. JAF 2026 Highlights Maritime Heritage and Coastal Architecture

    access_time21-11-2026 remove_red_eye709 personAnita Karyati
  4. Jakarta Strengthens ASEAN Cooperation on Climate, Transport, and Youth

    access_time20-11-2026 remove_red_eye652 personFolmer
  5. BORJU Markets 200 Local Products

    access_time20-11-2026 remove_red_eye619 personAnita Karyati