Penambahan PJU di Jakut Terkendala Lelang

Street Lights Addition in North Jakarta Hampered by Auction

Tuti Kurnia, North Jakarta head Sub-dept. of Industry and Energy, ensured that the public light installation in her area or at six sub-districts is not meet the target. There are six auction packages canceled by local Goods and Service Procurement Units (UPBBJ).

Our target was installing 7,315 public lights, but we only installed 6,600

"Our target was installing 7,315 public lights, but we only installed 6,600," she said, Wednesday (11/4).

The six canceled packages are Tanjung Priok I, Tanjung Priok II, Koja I, Koja II, Kelapa Gading I, and Penjaringan I. These packages total budget is Rp 3 billion.

25 Street Lights on Jalan Raya Bekasi Fixed

"We'll still run the maintenance for the existing spotlight," she added.

Meanwhile, Muhammad Chamdan, North Jakarta Head of UPPBJ, admitted that the packages must be eliminated due to no more time for installation.

"The installation needs 60 days," he stated.

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye869 personTiyo Surya Sakti
  2. TransJabodetabek Expansion, a Strategic Step to Increase Public Transportation Use

    access_time26-01-2026 remove_red_eye428 personFakhrizal Fakhri
  3. South Jakarta Tackles 38 Dengue Cases to Prevent Outbreak

    access_time02-02-2026 remove_red_eye416 personTiyo Surya Sakti
  4. Jakarta Prepares OMC and 200 Excavators to Prevent Flood

    access_time26-01-2026 remove_red_eye371 personDessy Suciati
  5. Jakarta Showers to Make Way for Partly Cloudy Skies

    access_time30-01-2026 remove_red_eye359 personDessy Suciati
close