Pemasangan Sheetpile Ciliwung Capai 81 Persen
.
photo Reza Hapiz - Beritajakarta.id

Sheet Pile Installation in Ciliwung River Touched 81 Percent

The installation of 2 km sheet pile along Ciliwung riverbank starting from Tongtek Bukit Duri bridge up to Jl KH Abdullah Syafii bridge Kampung Melayu has reached 81 percent. The remaining work will be done this month.

The project has reached 81 percent and the remaining project must be done this month

Teuku Iskandar, Ciliwung-Cisadane Flood Control Office (BBWSCC), explained flood will not hit Kampung Pulo if the sheet pile is already installed fully. In fact, the flood will hit Bukit Duri, Tebet, South Jakarta since the normalisation is not run yet.

Kodam Jaya's Troopers Cleaned Up Trash on Ciliwung River

“The project has reached 81 percent and the remaining project must be done this month,” said Iskandar, Monday (12/14).

He added that his side will create four water polder to accommodate water and anticipate flood. Each polder will get 1,000-2,000 later per second water pump.

“Those pumps will be used to suck water if Kampung Pulo is flooded,” he closed.

Linked News
Popular News indeks
  1. Takjil Supervision in Central Jakarta Begins Second Week

    access_time02-03-2025 remove_red_eye466 personBudhi Firmansyah Surapati
  2. Government Declares Ramadhan Starts on March 1, 2025

    access_time28-02-2025 remove_red_eye441 personBudhi Firmansyah Surapati
  3. Dishub: Lay Bay Remains Optimal to Support Public Transportation User Comfort

    access_time02-03-2025 remove_red_eye396 personAldi Geri Lumban Tobing
  4. Traffic Diverted on Jalan Jatinegara Barat as Floods Hit Jakarta

    access_time04-03-2025 remove_red_eye365 personNurito
  5. Jakarta ASN Working Hours Adjusted During Ramadan 2025

    access_time28-02-2025 remove_red_eye327 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik