You don't have javascript enabled. Good luck with that.
Pencarian
Ilustrasi Laporan Keuangan DKI
Untuk tahun 2014, sebanyak 433 miliar dianggarkan Sudin PU Tata Air Jakarta Barat. Dari total anggaran tersebut selama lima bulan, baru terserap .
photo istimewa - Beritajakarta.id

Low Budget Absorption by West Jakarta Water Management PU Sub-Dept

Rp 433 billion is budgeted by West Jakarta Water Management Public Works Sub-Department for the works this year. However, the total budget that has been absorbed is only 2.53 percent or around Rp 10 billion. Such number is very different compared to last year absorption which reached 45 percent at the same period.

In previous years, every region can hold their auction process respectively, so the project finished quick. But now, all auctions should be proceed in ULP, thus making everything becomes slow

Head of West Jakarta Water Management Public Works Sub-Department Planning Section, Santo, said the minimum budget absorbed this year is caused by the auction process which is done in one-stop services in Jakarta Goods and Services Procurement Services Unit (ULP).

In previous years, every region can hold their auction process respectively, so the project finished quick. But now, all auctions should be proceed in ULP, thus making everything becomes slow,” he explained, Monday (6/9).

43 Damaged Roads in East Jakarta Repaired

Santo detailed that from 41 activity packages of West Jakarta Water Management Public Works Sub-Department, there are only five projects that have been announced. As for the 2.53 percent of budget absorbed, it is from self-management activities in form of connecting channel dredging, lake dredging, and employee payment.

“Since the system now is through one-stop services, every region must wait ULP to finish the auction process. Meanwhile, ULP covers five regions plus Seribu Island regency where there are more than 7,000 activities. So, we had to stand in line,” he uttered.

According to Santo, the budget as much as Rp 433 billion will be used to conduct 200 activities, such as water channel normalization, water channel improvement and re-function, connecting channel dredging, lake dredging, goods procurement planning, pump house construction, culvert box repair, sluice repair, pump repair, and so forth. He is optimistic the remaining budget can be absorbed although the time left is only seven months to go.

“In 2013, with tight deadline and Rp 178 billion left, the budget could be absorbed for as much as 84 percent,” he told.

Linked News
Popular News indeks
  1. MSMEs Bazaar Held at Binus Anggrek Campus

    access_time30-10-2024 remove_red_eye950 personTP Moan Simanjuntak
  2. 250 High School Students in N. Jakarta Learn to Create Digital Content

    access_time01-11-2024 remove_red_eye653 personBudhi Firmansyah Surapati
  3. Satpol PP Expels Illegal Participants at Sudirman - Thamrin CFD

    access_time27-10-2024 remove_red_eye454 personBudhi Firmansyah Surapati
  4. South Jakarta City Government Accelerates Stop BABS

    access_time31-10-2024 remove_red_eye394 personTiyo Surya Sakti
  5. Traffic Arrangement Applied on Jalan Tambak

    access_time28-10-2024 remove_red_eye370 personAldi Geri Lumban Tobing