Bantargebang PLTSa Construction Has Reached 90 Percent

Jakarta Environment Agency Head, Isnawa Adji along with the Application and Assessment of Technology Agency’s (BPPT) IT Sector Chairman are reviewing the solar power plant (PLTSa) construction in Bantargebang Landfill, Bekasi, West Java.

Thus far its construction has touched 90 percent

Their arrival aims to see directly incinerators, workspaces, steam boiler machines, turbines, and garbage shelter.

"Thus far its construction has touched 90 percent," he expressed, Tuesday (2/12).

Anies Asked Bantar Gebang PLTSa to Be Accessible for Public

Adji explained that PLTSa would be able to manage garbage up to 100 tons per day to be converted into 500 kWh of electricity.

PLTSa itself is a pilot project for the use of garbage as a source of electricity and becomes the Environment Agency Strategic Area activity through the optimization of Bantar Gebang landfill.

"It becomes a part of Waste to Energy program," he said.

Linked News
Popular News indeks
  1. Central Jakarta Administration Acts Swiftly to Handle Kebon Kosong Fire

    access_time02-06-2026 remove_red_eye1417 personFolmer
  2. Jakarta Waives Motor Vehicle Tax Fines and Title Transfer Fees

    access_time01-06-2026 remove_red_eye854 personAldi Geri Lumban Tobing
  3. Commemorating Vesak, Jakarta Lights Up with Illumination of Jakarta 2026

    access_time30-05-2026 remove_red_eye653 personBudhi Firmansyah Surapati
  4. Seniors Participate in Pasti Bisa Berkarya at MRT Stations

    access_time02-06-2026 remove_red_eye602 personAldi Geri Lumban Tobing
  5. Krendang Fire Victims Receive Proper Support and Assistance

    access_time29-05-2026 remove_red_eye476 personBudhi Firmansyah Surapati