 Peremajaan Jalan Lingkungan di Empat Pulau Permukiman Mencapai 25 Persen
.
photo Suparni - Beritajakarta.id

Collector Road Maintenance Process in Four Islands Reaches 25 Percent

As long as 17 thousand meters collector roads in four islands of Thousand Islands are currently under maintenance. Its process currently reaches 25 percent.

We hope this project could finish in December

Thousand Islands Technical Work Unit (UKT) 2 Head, Sofyan mentioned, collector road maintenance is done in Tidung Island, Untung Jawa Island, Panggang Island, and Pramuka Island. This collector road maintenance project has been started since August.

"Until now, its process reaches 25 percent," he added, Tuesday (10/1).

Until December, Bina Marga Targeted to Concrete 107 Collector Roads in North Jakarta

He explained, 50 percent of building material used to repair the collector roads have been transported to the location. His side still has three months left to complete road maintenance.

In detail, there are 1,000 meters collector roads in Panggang Island; 9,000 meters in Pramuka Island; 2,000 meters in Tidung Island; and 5,000 meters in Untung Jawa Island that need to be repaired.

"We hope this project could finish in December," he stated.

Linked News
Popular News indeks
  1. Transjakarta Officially Opens School for Bus Drivers

    access_time20-11-2024 remove_red_eye1037 personAldi Geri Lumban Tobing
  2. Acting Governor Teguh: Coastal Seawall Construction Begins in 2025

    access_time20-11-2024 remove_red_eye903 personFolmer
  3. Legislator Ahmad Lukman Jupiter Wants PT FSTJ Add Shop Cars

    access_time19-11-2024 remove_red_eye544 personDessy Suciati
  4. PMPTSP Agency Launches PIN Greenvest to Prompt Green and Sustainable Investment

    access_time21-11-2024 remove_red_eye446 personAldi Geri Lumban Tobing
  5. Transjakarta Extends its Operation to 11 PM Today

    access_time19-11-2024 remove_red_eye379 personAldi Geri Lumban Tobing