Mud Dredging on Jalan F. Karang Anyar's Channel Targeted to Finish Today
access_time October 07 2019 02:03 PM remove_red_eye 829
Reported by Agung Supriyanto | Translated by Maria Inggita
Reported by Agung Supriyanto | Translated by Maria Inggita
Sawah Besar Water Resources (SDA) Sub-department Unit, Central Jakarta dredged 20 meters cubic of mud from channel located on Jalan F. Karang Anyar, Karang Anyar Urban Village.
Since September 26, we deployed 8 personnel and two trucks
Sawah Besar SDA Unit Head, Nanang Gusnadi stated, mud dredging is done to anticipate inundation.
"Since September 26, we deployed 8 personnel and two trucks to dredge and transport the mud to the landfill," he conveyed, Monday (10/7).
Channel on Jalan Bumi Indah Kebon Jeruk DredgedThis channel, he added, has length of 240 meters, width 60 centimeters and depth around 60 centimeters.
"Dredging process has reached 97 percent. Our target is to finish it today," he asserted.