Progress Pengerukan Waduk Ria Rio Capai 40 Persen
.
photo Nurito - Beritajakarta.id

Mud Dredging in Ria Rio Reservoir Has Reached 40 Percent

It is also carried out to minimize flooding on Jalan Perintis Kemerdekaan and residential areas in Kayu Putih

The mud dredging process in the Ria Rio Reservoir that has been ongoing since last February has reached 40 percent.

Every day, seven heavy equipments are deployed to dredge the reservoir, which covers about eight hectares with approximately six meters depth.

Pulo Mas Jaya to Revitalize Ria Rio Reservoir

East Jakarta Water Resources (SDA) Sub-agency's Maintenance Division Head Puryanto said that dredging was done to accommodate water in large quantities when rain pours.

"It is also carried out to minimize flooding on Jalan Perintis Kemerdekaan and residential areas in Kayu Putih," he said, Wednesday (6/10).

He added it was actually targeted to be completed within four months but impossible due to COVID-19.

"So we target it at least by the end of this year," he closed.

Linked News
Popular News indeks
  1. 21 Damaged Roads in Cilincing Repaired

    access_time11-07-2025 remove_red_eye550 personAnita Karyati
  2. Implementation of Free Schools Awaits Central Regulations, Pramono Says

    access_time11-07-2025 remove_red_eye460 personDessy Suciati
  3. Transjakarta Targets Planting 100,000 Mangroves

    access_time12-07-2025 remove_red_eye392 personBudhi Firmansyah Surapati
  4. Rano Karno Celebrates City's Anniversary with Kamal Residents

    access_time12-07-2025 remove_red_eye389 personFolmer
  5. Commission E Pushes for Accelerated Health Center Revitalization

    access_time11-07-2025 remove_red_eye369 personFakhrizal Fakhri

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik