Progress Pengerukan Waduk Ria Rio Capai 40 Persen
.
photo Nurito - Beritajakarta.id

Mud Dredging in Ria Rio Reservoir Has Reached 40 Percent

It is also carried out to minimize flooding on Jalan Perintis Kemerdekaan and residential areas in Kayu Putih

The mud dredging process in the Ria Rio Reservoir that has been ongoing since last February has reached 40 percent.

Every day, seven heavy equipments are deployed to dredge the reservoir, which covers about eight hectares with approximately six meters depth.

Pulo Mas Jaya to Revitalize Ria Rio Reservoir

East Jakarta Water Resources (SDA) Sub-agency's Maintenance Division Head Puryanto said that dredging was done to accommodate water in large quantities when rain pours.

"It is also carried out to minimize flooding on Jalan Perintis Kemerdekaan and residential areas in Kayu Putih," he said, Wednesday (6/10).

He added it was actually targeted to be completed within four months but impossible due to COVID-19.

"So we target it at least by the end of this year," he closed.

Linked News
Popular News indeks
  1. Monas Prepares to Greet Visitors This Eid Holiday

    access_time30-03-2025 remove_red_eye716 personDessy Suciati
  2. Jakarta Vice Governor Rano Wishes a Happy Eid al-Fitr 1446 Hijri

    access_time31-03-2025 remove_red_eye603 personFolmer
  3. Foul Smell Around JGC Clarified Not Coming from Rorotan RDF

    access_time28-03-2025 remove_red_eye439 personAldi Geri Lumban Tobing
  4. Odd-Even Policy in Jakarta Put on Hold for Eid Break

    access_time28-03-2025 remove_red_eye327 personAldi Geri Lumban Tobing
  5. 49,101 Local and Foreign Tourists Swarm Monas

    access_time02-04-2025 remove_red_eye285 personBudhi Firmansyah Surapati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik