Perbaikan Turap Kali Utan Kayu Capai 65 Persen

Utan Kayu River Sheet Piles Repair Has Reached 65 Percent

The Utan Kayu River sheet piles repair work in RW 05 and 12 Utan Kayu Selatan, Matraman, East Jakarta has touched 65 percent. Its repair has been ongoing since early July and is targeted to be complete by the end of this August.

This repair is urgent as if it is ignored, it will cause severe damage and will disrupt the existing drainage system

Agus, Field Supervisor for Matraman Sub-district Water Resources (SDA) Executing Unit acknowledged that the damage occurred when mud dredging was done, causing collapse in some parts due to age.

"This repair is urgent as if it is ignored, it will cause severe damage and will disrupt the existing drainage system," he expressed, Tuesday (8/4).

Inlet Setu Babakan Sheet Pile Repair Has Touched 80 Percent

He went on to say that there were two points that reached 100 meters in length on the west side of the location and one point with 100 meters on the east side.

Based on the information in the field, tens of officers were seen repairing sheet piles on Jalan Galur Sari Timur using a heavy equipment for transporting debris and material.

Linked News
Popular News indeks
  1. May Day: Transjakarta Service Adjustments

    access_time01-05-2026 remove_red_eye2182 personAldi Geri Lumban Tobing
  2. Betawi Eid in Ciganjur Goes Lively

    access_time02-05-2026 remove_red_eye2152 personTiyo Surya Sakti
  3. Dinkes Sets Up Health Posts for May Day Events

    access_time01-05-2026 remove_red_eye1954 personDessy Suciati
  4. Malaka Jaya Residents Take Part in Waste Sorting Program

    access_time03-05-2026 remove_red_eye1924 personNurito
  5. City Deploys Massive Cleanup Force for May Day at Monas

    access_time01-05-2026 remove_red_eye1909 personAldi Geri Lumban Tobing