TIM Revitalization Process Reaches 40.86 Percent
Reported by Wuri Setyaningsih | Translated by Maria Inggita
Taman Ismail Marzuki (TIM) revitalization work keeps running even in the midst of COVID-19 pandemic situation.
In the midst of COVID-19 pandemic, TIM revitalization work applies a strict health protocol
Entering the 67th week, revitalization progress has reached 40.86 percent for the first phase. Particularly, the park parking building that has even reached 95.59 percent or has entered the finishing stage.
"We also work on finishing stage for roof floor at park parking building," said Melisa Sjach, Corporate Communication Manager of PT. Jakarta Propertindo (Jakpro), Tuesday (11/3).
TIM Revitalization Progress Reaches 37.60 PercentWater proofing work with soaking test process has also entered the final stage. While construction process for library and art guesthouses has reached 20.39 percent. The current work process includes excavating the basement, ironing, and pile cap. While the work in library and art guesthouses has entered strutting and pool construction stages.
"In the midst of COVID-19 pandemic, TIM revitalization work applies a strict health protocol," she asserted.
The workers also routinely carry out rapid test. His side hopes TIM revitalization work can increase people's enthusiasm and optimize artists' creative ideas.
"We hope the new face of TIM that is more magnificent, modern, and monumental can encourage art communities to be more productive," he conveyed.