Channel Repair Work on Jalan Cendrawasih Has Reached 75 Percent
access_time December 07 2020 04:51 PM remove_red_eye 1090
Reported by Rudi Hermawan | Translated by Nugroho Adibrata
Reported by Rudi Hermawan | Translated by Nugroho Adibrata
It is targeted to be complete on December 20
The water channel repair work on Jalan Cendrawasih X, RT 06/17, Cengkareng Barat, Cengkareng, West Jakarta has reached 75 percent.
Clean Water and Wastewater Raw Water Handling System Maintenance Division Head Wawan Kurniawan said the repair around the Cendrawasih GOR along 215 meters long with 60 centimeters high had been ongoing since November 12.
36 Damaged Road Points in Central Jakarta Being Repaired"To do it, we have sent 24 personnel to the location. It is targeted to be complete on December 20," he said, Monday (12/7).
He explained the channel itself is the outlate of the Cendrawasih reservoir, thus water can flow properly and does not inundate residential areas.
"This outlate is on the residents' channel, precisely after leaving the Cendrawasih GOR complex," he stated.