West Jakarta SDA Completes Stilling Basin Construction in Kedoya Utara
Reported by Rudi Hermawan | Translated by Maria Inggita
West Jakarta Water Resources (SDA) Sub-agency has completed stilling basin construction and channel normalization in Green Garden, Kedoya Utara, Kebon Jeruk.
Its construction has completed since December 28
West Jakarta SDA Sub-agency's Flood Control Maintenance System for Clean Water and Wastewater Section Head, Wawan Kurniawan stated, stilling basin construction work has been started since November 2020.
It was built beside Kedoya Utara gas station (SPBU), Kebon Jeruk, with width 2 meters and length 40 meters.
SDA Continues Stilling Basins Construction Work on Jl. Boulevard Raya"Its construction has completed since December 28. Now, we are currently installing British Reinforced Concrete (BRC) fence," he informed, Tuesday (1/5).
Moreover, his side also completed channel normalization work at Green Garden Residential Houses Block A14, RT 012/05.
Initially, that water channel has width 50 centimeters and depth 30 centimeters then it widened into 150 centimeters with depth 1 meter.
"Stilling basin construction and channel widening are carried out to overcome inundation in Green Garden," he said.