SDA Continues Stilling Basins Construction Work on Jl. Boulevard Raya

Stilling basins construction on Jalan Boulevard Raya, Kelapa Gading, North Jakarta is accelerated thus it can finish in March 2021.

Current progress has reached about 50 percent

Kelapa Gading Sub-district Water Resources (SDA) Unit Head, Citrin Indriyanti mentioned, there are total 11 stilling basins that will be built in the location. The construction has been carried out since mid October 2020.

"Current progress has reached about 50 percent. We will continue the work in this early year," she added, Saturday (1/2).

Crossing Channel Construction on Jalan Latumenten Completed

According to her, there was a delay in building stilling basins because her side needed to prioritize flood anticipation work in several other locations. Thus the field officers were assigned into several locations at the same time.

Each stilling basin has average length 15 meters with width 3 meters and depth 1.3 meters. So far, five stilling basins have been completed.

"Our target is to finish it as soon as possible, which expected in March," she conveyed.

Linked News
Popular News indeks
  1. Fire at Pondok Bambu Allegedly Triggered by Electrical Short

    access_time19-05-2026 remove_red_eye1356 personNurito
  2. Telkomsel Digiland Run 2026 Parking Lot List: Check Now!

    access_time14-05-2026 remove_red_eye1255 personAldi Geri Lumban Tobing
  3. Governor Pramono Named Vice Chair of C40 Cities Steering Committee

    access_time18-05-2026 remove_red_eye985 personAldi Geri Lumban Tobing
  4. Inundation on DI Panjaitan Road Recede

    access_time20-05-2026 remove_red_eye819 personNurito
  5. Dharma Jaya Ready for Thousands of Eid al-Adha Sacrifices

    access_time20-05-2026 remove_red_eye613 personAldi Geri Lumban Tobing