Perbaikan Breakwater di Sisi Timur Laut Pulau Untung Jawa Rampung

Breakwater Repair Work in Northeast Side of Untung Jawa Island Completed

Thousand Islands Water Resources (SDA) Sub-agency completed breakwater repair in the northeast side of Untung Jawa Island, Untung Jawa Island Urban Village, South Thousand Islands Sub-district.

We rearrange 249 tetrapods thus it can withstand the waves well

Thousand Islands SDA Sub-agency Head, Hendri conveyed, in this repair, his side rearranged the disordered tetrapods along more than 600 meters because of wave.

"We rearrange 249 tetrapods thus it can withstand the waves well. This work has been started since last week and completed yesterday," he mentioned, Friday (7/2).

Breakwater Repair Work on East Side of Karya Island Has Reached 80 Percent

In this breakwater repair work, his side deployed 14 personnel as well as raft and one heavy equipment ship unit.

"After rearranging tetrapods, we hope it can be stronger to hold high waves and prevent abrasion," he conveyed.

Linked News
Popular News indeks
  1. MRT Jakarta Integrates Ticket Payments with JakLingko from October 12

    access_time10-10-2026 remove_red_eye560 personAldi Geri Lumban Tobing
  2. Jakarta Administration Steps Up Proactive Fire Prevention Efforts

    access_time09-10-2026 remove_red_eye550 personDessy Suciati
  3. New Kelapa Gading-Pulogadung Road to Ease Traffic and Improve Access

    access_time10-10-2026 remove_red_eye539 personAldi Geri Lumban Tobing
  4. Kramat Pulo Fire Survivors Get Help Replacing School Documents

    access_time09-10-2026 remove_red_eye526 personFolmer
  5. Basic Supplies Distributed to Pinang Ranti Fire Survivors

    access_time09-10-2026 remove_red_eye512 personNurito