Pengerukan Waduk Cilangkap Capai 30 Persen

Contractor Targets to Finish Cilangkap Reservoir Dredging Work in November

Dredging is carried out to four meters depth

The 5-hectare Cilangkap Reservoir dredging work, which is located in RW 01 Cilangkap, Cipayung, East Jakarta has currently touched 30 percent and is targeted to be complete in the forthcoming November.

Clay Dredged from Munjul Reservoir Used to Expand Burial Ground at TPU Bambu Apus

It has two cross sections and is located on the border of Cilangkap and Munjul urban villages.

East Jakarta Water Resources (SDA)'s Maintenance Division Head, Puryanto said, as many as four heavy equipment had been alerted to the location, consisting of three heavy equipment type standard and one unit of long arm.

"Dredging is carried out to four meters depth," he stated, Friday (7/23).

According to him, its existence was aimed at overcoming flooding or inundation in the surrounding area, such as in Cilangkap, Setu, Lubang Buaya.

"It is done to accommodate water in large quantities when it rains. Moreover, It was previously abandoned and used by residents for illegal paid fishing," he concluded.

Linked News
Popular News indeks
  1. Open for All: Jakarta City Hall Welcomes Visitors for Namu Balai Kota

    access_time03-10-2026 remove_red_eye680 personDessy Suciati
  2. Transjakarta Reaffirms Ban on Busking in Mikrotrans and Bus Stops

    access_time02-10-2026 remove_red_eye510 personAldi Geri Lumban Tobing
  3. Jakarta Builds Five New Animal Health Centers to Expand Veterinary Services

    access_time30-09-2026 remove_red_eye506 personAldi Geri Lumban Tobing
  4. Commission D Supports Reserve Fund for Long-Term Infrastructure

    access_time02-10-2026 remove_red_eye481 personFakhrizal Fakhri
  5. 1,500 Runners and Pets Hit the Track for World Rabies Day Run 2026

    access_time03-10-2026 remove_red_eye473 personAnita Karyati