Channel Normalization Work in Gang Udang Cempaka Baru has Reached 73.91 Percent

Ahead of rainy season, Central Jakarta Water Resources (SDA) Sub-agency accelerates its work to prevent inundation and flood. One of its work is normalizing water channel in Gang Udang, RT 01/08, Cempaka Baru Urban Village, Kemayoran Sub-district.

From target 694 meters, current progress has reached 513 meters or 73.91 percent

Central Jakarta SDA Sub-agency's Maintenance Section Supervisory Staff, Yusuf Sumardani stated, normalization work was done by installing u-ditch. This work had been carried out since June 2021 and is targeted to be completed by the end of October 2021. Normalization on this channel was requested by residents through Musrenbang because the area is often flooded when it rains heavily.

"From target 694 meters, current progress has reached 513 meters or 73.91 percent. We deploy 14 personnel and u-ditch installation is carried out manually," he informed, Thursday (9/23).

Disdukcapil Provides Solutions to Residents Related Invalid NIK and KK

This normalization work was carried out by digging that 70-centimeter wide channel with 55-centimeter height. Every day, his side transported 5 cubic meters mud sedimentation. After that, his side installed 40x40x120 centimeters u-ditch.

"After installing u-ditch, we will close the channel to make it neat," he mentioned.

Cempaka baru Urban Vilalge Consultative Body (LMK) Member, Yuli Kusdianto conveyed, channel normalization was carried out to follow up proposal submitted in Musrenbang to be realized this year.

"Thank God, this normalization can finally be carried out, because the location is very low and when it rains, it often cause flood thus many residents complain. Even though it is only half way, the results can already be seen when it rained continuously yesterday," she said.

Linked News
Popular News indeks
  1. Transjakarta Officially Opens School for Bus Drivers

    access_time20-11-2024 remove_red_eye1036 personAldi Geri Lumban Tobing
  2. Acting Governor Teguh: Coastal Seawall Construction Begins in 2025

    access_time20-11-2024 remove_red_eye902 personFolmer
  3. Legislator Ahmad Lukman Jupiter Wants PT FSTJ Add Shop Cars

    access_time19-11-2024 remove_red_eye544 personDessy Suciati
  4. PMPTSP Agency Launches PIN Greenvest to Prompt Green and Sustainable Investment

    access_time21-11-2024 remove_red_eye446 personAldi Geri Lumban Tobing
  5. Transjakarta Extends its Operation to 11 PM Today

    access_time19-11-2024 remove_red_eye379 personAldi Geri Lumban Tobing