Ini Progres Program Pengendalian Banjir 942 per 22 Mei 2022
....
photo Istimewa - Beritajakarta.id

Here is the Progress of 942 Program as of May 22, 2022

The Jakarta Government's super-priority activity to build and rehabilitate nine polders, four reservoirs, and two rivers (942 Program) is still ongoing.

The work in each location is still ongoing with varying progress

The nine polders are located in Muara Angke, Teluk Gong, Mangga Dua, Kelapa Gading, Pulomas, Marunda JGC, Green Garden, Kamal, and Tipala Pump - Adhyaksa Pump.

Meanwhile, four reservoirs are located in Pondok Ranggon Reservoir, Wirajasa Retention Basin, Brigief Reservoir, and Lebak Bulus Reservoir.

Here is the Progress of 942 Flood Management Programs

Then, two rivers are located in the Maritime Museum Canal Crossing Channel (Sodetan) of Kali Besar River and Ciliwung River downstream in the Pasar Baru area.

Jakarta Water Resources (SDA) Agency Secretary Dudi Gardesi Asikin conveyed the Government had allocated Rp 1 trillion for the multi-year infrastructure program (2021-2022) from central government loan funds through the 2021 National Economic Recovery (PEN) program.

The 942 program was one of Jakarta's important efforts to handle and overcome inundation and flooding in five areas of Jakarta.

"The work in each location is still ongoing with varying progress," he said, Friday (5/27).

The polder, he explained, is an area drainage system equipped with infrastructure in form of pumps, sluice gates, and long storage to accommodate rainwater from the area. Technically, the polder will divide water flow into several rivers to minimize flooding in an area.

"Through polder system, water discharge from an area will be accommodated and channeled to rivers which are controlled through sluice gates and water pumps," he mentioned.

According to him, the polder catchment area in each location varied between 100-700 hectares. Likewise, the scope of polder work, such as new pumps, sluice gates, parapet, and sheet piles, increased pump capacity, garbage filters, rotary screen, and hoist crane.

"Polder will be equipped with supporting infrastructure according to the needs, existing conditions, and location characteristics," he added.

According to him, reservoir construction is targeted to reduce flood discharge in the river flow system. It was also designed with the concept of 'green and blue' and used as a public space to preserve local wisdom.

"River capacity is also improved to increase capacity for water discharge, control regional flooding, and arrange riverbanks," he stated.

The following is the progress of 9 polders, 4 reservoirs, and 2 rivers construction (942 program) as of March 22, 2022:

Polder Cluster

- Construction of Kelapa Gading Polder (Betik and Artha Gading) and Pulomas Polder reached 25.43 percent (deviation of 0.11 percent)

- Construction of Marunda Sub Polder (JGC-Metland) and Tipala Pump-Adhyaksa Pump reached 8.93 percent (deviation -7.52 percent)

- Construction of Muara Angka, Teluk Gong, and Mangga Dua Polders reached 14.42 percent (deviation -9.56 percent)

- Construction of the Green Garden Polder and its accessories reached 15.12 percent (deviation -3.32 percent)

- Construction of the Kamal Polder system (pump, slice gates, and accessories) reached 14.53 percent

Reservoir and Retention Basin Cluster

- Construction of Pondok Ranggon Reservoir and Wirajasa Retention Basin, as well as its accessories reached 40.93 percent (deviation of 0.81 percent)

- Construction of Brigief Reservoir and Lebak Bulus Reservoir as well as its accessories reached 27.15 percent (deviation of 0.18 percent)

River Cluster

- Construction or work on adding capacity of Kali Besar River and Maritime Museum Canal Crossing Channel reached 20.33 percent (deviation -1.66 percent)

- Construction or work on adding capacity of Ciliwung River downstream in Pasar Baru reached 20.84 percent (deviation -6.81 percent)

Linked News
Popular News indeks
  1. Transjakarta Officially Opens School for Bus Drivers

    access_time20-11-2024 remove_red_eye1036 personAldi Geri Lumban Tobing
  2. Acting Governor Teguh: Coastal Seawall Construction Begins in 2025

    access_time20-11-2024 remove_red_eye902 personFolmer
  3. Legislator Ahmad Lukman Jupiter Wants PT FSTJ Add Shop Cars

    access_time19-11-2024 remove_red_eye544 personDessy Suciati
  4. PMPTSP Agency Launches PIN Greenvest to Prompt Green and Sustainable Investment

    access_time21-11-2024 remove_red_eye446 personAldi Geri Lumban Tobing
  5. Transjakarta Extends its Operation to 11 PM Today

    access_time19-11-2024 remove_red_eye379 personAldi Geri Lumban Tobing