Normalisasi Jl Cempaka Putih Tengah Sudah 70 Persen

Next Week, Channel Repair on Jalan Cempaka Putih Finished

The Cempaka Putih Sub-district Water Resources (SDA) Executing Unit keeps accelerating the repair of the water channel on Jalan Cempaka Putih Tengah, Cempaka Putih Timur Urban Village.

The progress has touched 70 percent through 16 workers

It has been ongoing since June 20 and is targeted to be finished next week.

Cempaka Putih Sub-district SDA Executing Unit Head Subandi said the repair was carried out, as many points were damaged. As a result, it was unoptimal to accommodate water and could cause flooding.

Cawang Reservoir Outlet Construction Accelerated

"The thickness of the mud reaches 10 centimeters. Thus far, around 20 cubic meters of mud have been transported and then disposed into the Ancol PLTU, North Jakarta," he explained, Thursday (6/30).

Aside that, the workers also replaced the channel material with a 40x40-centimeter U-ditch, complete with a concrete slab cover.

"The normalized total is 75 meters. The progress has touched 70 percent through 16 workers," he stated.

Linked News
Popular News indeks
  1. Jakarta Endorses New Housing Project for Residents on Railway Embankments

    access_time28-03-2026 remove_red_eye2394 personDessy Suciati
  2. Deputy Governor Watches Pelangi di Mars with Orphans

    access_time27-03-2026 remove_red_eye860 personTiyo Surya Sakti
  3. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye690 personTiyo Surya Sakti
  4. Pramono Calls for Enhanced Synergy at DPRD Post-Eid Gathering

    access_time30-03-2026 remove_red_eye679 personDessy Suciati
  5. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye614 personTiyo Surya Sakti