Channel on Jalan H Agus Salim Being Normalized
access_time October 29 2023 04:06 PM remove_red_eye 493
Reported by Wuri Setyaningsih | Translated by Nugroho Adibrata
Reported by Wuri Setyaningsih | Translated by Nugroho Adibrata
The channel normalization work on Jalan H Agus Salim, Gondangdia, Menteng, Central Jakarta has reached 80 percent.
The normalization is carried out up to 40 meters of channel
Central Jakarta Water Resources (SDA) Sub-agency Acting Governor, Adrian Mara Maulana said the normalization was carried out, because the channel was old.
"The normalization is carried out up to 40 meters of channel," he expressed, Sunday (10/29).
SDA Agency Builds New Sheet Pile in Munjul Reservoir AreaIt had been ongoing since October 13 and involved 17 personnel. It was targeted for completion on November 2, 2023.
"We send one excavator unit to replace the u-ditch with dimensions of 80 centimeters," he explained.
Thus far, it has entered the hearth stage or reached 80 percent.
"Hopefully, the channel can maximally accommodate water in the rainy season," he hoped.