 Progres Normalisasi Saluran Air Jalan Murtado XIII Capai 40 Persen

Damaged Channel Repairs in Paseban Accelerated

The Central Jakarta Water Resources (SDA) Sub-agency is speeding up channel repairs on Jalan Murtado XIII, RT 15/06, Paseban, Senen.

Some of the sheet piles are damaged

Senen Sub-district SDA Executing Unit Head, Zulfahmi Baco said the channel repairs at the location are a follow-up to residents' complaints during the Musrenbang considering that the condition of the channel has a lot of damage and narrowing.

"Some of the sheet piles are damaged," he expressed, Wednesday (6/12).

Sidewalk Repair on Jalan Pasar Senen Completed

He explained the channel was originally 40 centimeters wide and 60 centimeters high. Because of severe damage, the channel had to be replaced with new ones.

It has been ongoing since Friday (5/17) and involved 11 personnel every day. Predictably, the overall work will be completed by the end of June 2024.

"We are simultaneously installing the u-ditch. The progress to date is around 40 percent," he added.

The repair received appreciation from one of the residents in RW 06, Paseban, Maula (35). "Hopefully, it can be finished on time before the rainy season," he closed.

Linked News
Popular News indeks
  1. Jakarta Council Begins Deliberations on New Population and Housing Bylaws

    access_time21-08-2026 remove_red_eye1933 personFakhrizal Fakhri
  2. Pramono Vows to Prioritize Jakarta’s Strategic Development

    access_time22-08-2026 remove_red_eye1025 personDessy Suciati
  3. Rano: CIEIE 2026 to Catapult Jakarta’s MSMEs onto the International Stage

    access_time25-08-2026 remove_red_eye720 personBudhi Firmansyah Surapati
  4. Pramono Pushes for Partnership Between New Toto Tentrem and Tarakan Hospitals

    access_time24-08-2026 remove_red_eye639 personDessy Suciati
  5. New LRT Jakarta Route Set for Official Launch on August 26

    access_time22-08-2026 remove_red_eye499 personDessy Suciati