You don't have javascript enabled. Good luck with that.
Pencarian
Pengerukan Lumpur di Kolam Retensi Taman Sepat Terus Dioptimalkan
....
photo Andri Widiyanto - Beritajakarta.id

Mud Dredging at Sepat Park Retention Pool Accelerated

The South Jakarta Water Resources Sub-agency (SDA) is speeding up the mud dredging process at the Taman Sepat Retention Pool, Kebagusan, Pasar Minggu.

Every day, personnel can dredge 50 cubic meters of mud

South Jakarta SDA Sub-agency's Heavy Equipment Monitoring Officer, Mahardika said the dredging was conducted to anticipate the buildup of mud and maximize Sepat Park's function as a retention pond.

"The thickness of the mud reaches one meter deep. However, our personnel only dredged it to 50 centimeters deep," he expressed, Monday (6/24).

PPSU Clean Waste from RW 03 Water Channel

He explained the dredging, which started on May 18, was targeted to be completed in the next one to three months.

"Every day, personnel can dredge 50 cubic meters of mud from this retention pond," he explained.

He hoped that it could restore the capacity of the retention pond to normal. So, it can reduce and overcome the potential for flooding in the area around Pasar Minggu.

"Hopefully, it can run smoothly and quickly," he stated.

Linked News
Popular News indeks
  1. Jakarta-France Strengthen Cooperation in Various Sectors

    access_time11-04-2025 remove_red_eye521 personDessy Suciati
  2. Three South Jakarta Parks Set for Revitalization and 24-Hour Operation

    access_time12-04-2025 remove_red_eye453 personDessy Suciati
  3. 60 Joint Personnel Conduct Community Work in Karet Tengsin

    access_time13-04-2025 remove_red_eye395 personBudhi Firmansyah Surapati
  4. Free Transportation Services to Facilitate Residents' Mobility

    access_time17-04-2025 remove_red_eye274 personDessy Suciati
  5. Jakarta to be Designed as a Film City

    access_time13-04-2025 remove_red_eye273 personFakhrizal Fakhri

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik