Channel Dredging on Jalan Kramat Bunder Dredged from Mud
access_time June 27 2024 06:14 PM remove_red_eye 254
Reported by Budhi Firmansyah Surapati | Translated by Nugroho Adibrata
Reported by Budhi Firmansyah Surapati | Translated by Nugroho Adibrata
As many as 33.6 cubic meters of mud are dredged from the channel on Jalan Kramat Bunder, RW 01, Kramat Urban Village, Senen.
If it is not done, it will trigger flooding in the rainy season
Senen Sub-district SDA Executing Unit Head, Zulfahmi Baco expressed the dredging is a routine agenda to anticipate blockages and flooding.
"If it is not done, it will trigger flooding in the rainy season," he said, Thursday (6/27).
Mud Dredging at Sepat Park Retention Pool AcceleratedHe explained the work involved 12 personnel started in May 13, 2024. The channel itself has a width and a length of 207 meters with 80 centimeters long.
"The thickness of the channel mud has reached 20 centimeters. Currently, the work is complete already," he explained.
The work received appreciation from one of the residents from RW 01 Kramat Urban Village, Ari.
"If it is not dredged, the overflowing channel water won't only inundate the road, but also the surrounding residential areas," he closed.