Pembangunan Saluran di Jalan KH. M. Naim II Rampung Agustus

August, Channel Normalization on Jalan KH M Naim II Completed

The South Jakarta Water Resources Sub-agency (SDA) targets to finish the water channel normalization in the forthcoming August which is located on Jalan KH. M. Naim II, RT 02/11, Cipete Utara Urban Village, Kebayoran Baru.

It has been ongoing since May 2024

Kebayoran Baru SDA Executing Unit Head, Sutopo said the channel as long as 105 meters was normalized using U-Ditch concrete measuring 60x40 centimeters by five task force personnel with the support of an excavator.

"It has been ongoing since May 2024," he expressed, Wednesday (7/10).

Channel Normalization at Gang Pertamina Reaches 50 Percent

Cipete Utara Urban Village Head, Supriyanto added that normalization was done considering the condition was too small and unoptimal in accommodating the rainwater when it rained. As a result, it caused flooding.

After it was done, it could minimize flooding due to overflowing water from the canal.

"I urge residents to support development in their environment and not to throw trash carelessly," he said.

Linked News
Popular News indeks
  1. Temporary Crosswalk to Be Built at Tendean Pedestrian Bridge Site

    access_time18-07-2026 remove_red_eye1748 personFakhrizal Fakhri
  2. China-Based Training Equips PR Professionals and Journalists for Digital Media Transformation

    access_time19-07-2026 remove_red_eye1455 personFakhrizal Fakhri
  3. Rano Challenges Jakarta Provoke Organizers to Hold Exhibition Along Sudirman-Thamrin

    access_time18-07-2026 remove_red_eye1064 personBudhi Firmansyah Surapati
  4. Jakarta Supports Social Media Restrictions for Children

    access_time20-07-2026 remove_red_eye1033 personFakhrizal Fakhri
  5. Gas Stove Leak Sparks Fire, Gutting Five Rented Houses on Jalan Kayu Tinggi

    access_time17-07-2026 remove_red_eye972 personNurito