Continuation of Embankment Construction in Northern Tidung Island to Complete in November
Reported by Anita Karyati | Translated by Rizky Mawardi
Seribu Island Water Resource Sub-agency continues the construction of embankment in northern Tidung Island up to west side of Port, RT 07/03, Tidung Island Urban Village, Seribu Selatan Sub-district.
We deploy 21 Blue Taskforce personnel
Seribu Island Water Resource Sub-agency's Coordinator, Ahmad Sofyan, said the construction of the massive cube embankment is a continuation of the northern side in RT 06/03 which has been completed along 135 meters.
Breakwater Repair on East Side of Panggang Island Completed"The continuation of this construction is responding local resident's request in Musrenbang 2024," he said, Tuesday (9/3).
Sofyan explained that the construction of the continuation of the embankment is carried out along 100 meters with a width of 80 centimeters and a height of 160 centimeters (four layers of massive cubes).
"We deploy 21 Blue Taskforce personnel," he added.
According to him, the construction has been running since September 2, 2024 and is targeted to complete in 60 days.
"Hopefully, the embankment can prevent the island from abrasion and protect residential areas from being hit by waves," he continued.
Meanwhile, one of RW 03 residents, Tidung Island Urban Village, Suratno (52), appreciated the personnel for responding the request.
"Residents will be safer and more comfortable. Tidal wave can be prevented from entering residential areas," he hoped.