Pembuatan Saluran Air di Jalan Mawar Sudah 70 Persen

New Water Channel on Jalan Mawar Under Construction

A new water channel is being constructed on Jalan Mawar, RT 08/13, Bintaro Urban Village, Pesanggrahan Sub-district, aimed at addressing flooding issues.

It is very good and organized

"The work progress has touched 70 percent and is targeted to be completed by the end of this year," said Pesanggrahan Water Resources (SDA) Executing Unit Head, Chairul Anwar, Monday (7/21).

He explained, this 120-meter long water channel construction uses a 40-HD U-Ditch and has been underway since June 19, 2025. This is done manually with the involvement of four personnel.

Channel on Jalan Pondok Gede Finally Clean from Mud

He hoped that it could minimize flooding, especially when it rains.

"And also last long," he hoped.

The work received appreciation from one of the locals, Heru.

"It is very good and organized," he stated.

Linked News
Popular News indeks
  1. Fire at Pondok Bambu Allegedly Triggered by Electrical Short

    access_time19-05-2026 remove_red_eye1384 personNurito
  2. Governor Pramono Named Vice Chair of C40 Cities Steering Committee

    access_time18-05-2026 remove_red_eye1018 personAldi Geri Lumban Tobing
  3. Inundation on DI Panjaitan Road Recede

    access_time20-05-2026 remove_red_eye845 personNurito
  4. Dharma Jaya Ready for Thousands of Eid al-Adha Sacrifices

    access_time20-05-2026 remove_red_eye655 personAldi Geri Lumban Tobing
  5. Rasuna Said Car-Free Day to Return in June 2026

    access_time16-05-2026 remove_red_eye637 personAldi Geri Lumban Tobing