photo Reza Hapiz - Beritajakarta.id

MRT's Depot Construction Awaits Building Demolishment

The Director of PT MRT Jakarta, Dono Boestami acknowledged, Lebak Bulus Station construction for mass rapid transit project currently is still in the early phase and it still ongoing.

We wait building demolishment in Lebak Bulus station and ex-Polri residential to build depot there

According to him, there are two layers construction, track column from Lebak Bulus – Fatmawati is being prepared at the elevated station, while for underground station in the phase of traffic engineering.

We wait building demolishment in Lebak Bulus station and ex-Polri residential to build depot there. While there is also mosque relocation,” he uttered, Thursday (7/9).

MRT Project Still Reaches 30 Percent

Meanwhile, on the south direction, his side is still await some lands which City Administration have not take over to contractor.

Linked News
Popular News indeks
  1. Rano: Pancasila is the Big House for Indonesia's Diversity

    access_time02-06-2025 remove_red_eye526 personBudhi Firmansyah Surapati
  2. Friendly Countries' Ambassadors Participate in Famtrip to Seribu Islands

    access_time05-06-2025 remove_red_eye411 personAldi Geri Lumban Tobing
  3. Transjabodetabek Bogor–Blok M Route and Corridor 13 Extension Begin Operations

    access_time05-06-2025 remove_red_eye400 personDessy Suciati
  4. S. Jakarta Mayor: Idul Adha is a Moment to Enhance Compassion Among One Another

    access_time06-06-2025 remove_red_eye282 personTiyo Surya Sakti
  5. No Odd-Even Restrictions in Jakarta on June 6-9, 2025

    access_time03-06-2025 remove_red_eye274 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik