Pembangunan MRT Terhambat di Cipete dan Haji Nawi
.
photo Reza Hapiz - Beritajakarta.id

MRT's Depot Construction Awaits Building Demolishment

The Director of PT MRT Jakarta, Dono Boestami acknowledged, Lebak Bulus Station construction for mass rapid transit project currently is still in the early phase and it still ongoing.

We wait building demolishment in Lebak Bulus station and ex-Polri residential to build depot there

According to him, there are two layers construction, track column from Lebak Bulus – Fatmawati is being prepared at the elevated station, while for underground station in the phase of traffic engineering.

We wait building demolishment in Lebak Bulus station and ex-Polri residential to build depot there. While there is also mosque relocation,” he uttered, Thursday (7/9).

MRT Project Still Reaches 30 Percent

Meanwhile, on the south direction, his side is still await some lands which City Administration have not take over to contractor.

Linked News
Popular News indeks
  1. Government Declares Ramadhan Starts on March 1, 2025

    access_time28-02-2025 remove_red_eye409 personBudhi Firmansyah Surapati
  2. Takjil Supervision in Central Jakarta Begins Second Week

    access_time02-03-2025 remove_red_eye399 personBudhi Firmansyah Surapati
  3. Dishub: Lay Bay Remains Optimal to Support Public Transportation User Comfort

    access_time02-03-2025 remove_red_eye374 personAldi Geri Lumban Tobing
  4. Orderly Sidewalk Operation Targets Many Streets in Jakarta

    access_time27-02-2025 remove_red_eye369 personAldi Geri Lumban Tobing
  5. Jakarta ASN Working Hours Adjusted During Ramadan 2025

    access_time28-02-2025 remove_red_eye315 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik