Sheet Pile Construction in Kampung Pulo Completed
Reported by Nurito | Translated by Nugroho Adibrata
The sheet pile construction as long as two kilometers from Kampung Pulo until bridge fof jl KH Abdullah Syafii, Kampung Melayu, Jatinegara, East Jakarta is completed. While the parapet wall construction has reached 95 percent.
Ciliwung normalization in Kampung Pulo continues to be accelerated. It is targeted to be completed by the end of May. As for the sheet pile has completed
Section Head of Implementer for Ciliwung-Cisadane Flood Control Office (BBWSCC), Bastari disclosed normalization of Ciliwung River in Kampung Melayu area is almost complete. For parapet wall that built as long as 1.7 kilometers has reached 95 percent.
"Ciliwung normalization in Kampung Pulo continues to be accelerated. It is targeted to be completed by the end of May. As for the sheet pile has completed," he expressed, Thursday (5/19).
June, Sheet Pile Installation in Bukit Duri BeginsAccording to him, parapet wall construction does not reach two kilometers because some position of the river is high enough. So it is not wholly and only until the back of the Jatinegara Barat Flat. While the flat until the bridge, Jalan Abdullah Syafii is not fitted with parapet wall.
Besides that, his side also installs U-dith concrete. From total length of two kilometers, the installation has reached 60 percent.