Pembangunan Jalan Tembus Kelapa Gading Terkendala Bangunan Warga

Throughway Construction Project in Kelapa Gading Hampered

The construction of throughway that connects Jalan Boulevard Timur with Jalan Perintis Kemerdekaan is meeting obstacles. The reason is the existence of 34 buildings belong to residents living in RT 05/02, Pegangsaan Dua Urban Village, Kelapa Gading Sub-District, North Jakarta, that stand between the throughway project.

The project has been running for three years. Therefore, if after Eid ul Fitr the project still has not finished, we’ll take affirmative action

The residents who live on a land as wide as 4,000 meters insist to stay there because there is no compensation deal yet with the landowners. The land is legally owned by two owners initialed P and L. However, North Jakarta Administration in 2012 has paid the compensation money of the land in accordance to NJOP.

Prone of Thugs, Kelapa Gading Shop House Controlled

North Jakarta Secretary, Junaedi, said that negotiation is still ongoing with the landowners and residents. In this matter, North Jakarta Administration only acts as mediator to finish the problem immediately.

“Both parties have met yesterday. The landowners offered 20 percent of the 2012 NJOP price, but the residents haven’t accepted it,” he told, Thursday (6/19).

According to Junaedi, the residents have admitted that they do not have legality on that land. However, they demand for compensation because they have occupied the land for dozens of years.

Meanwhile, North Jakarta Mayor, Heru Budi Hartono, hopes the mediation not to be protracted since the impact could potentially make the completion of throughway construction project late.

The project has been running for three years. Therefore, if after Eid ul Fitr the project still has not finished, we’ll take affirmative action,” he asserted.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1589 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1439 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1303 personFolmer
  4. Jalan Kebon Kelapa I Repaved

    access_time07-07-2026 remove_red_eye1096 personNurito
  5. Pramono Inaugurates Mayapada Hospital to Improve Healthcare Services

    access_time09-07-2026 remove_red_eye967 personDessy Suciati