Pembangunan MRT Jakarta Capai 95,97 Persen

Phase I MRT Development Reaches 95.97 Percent

Physical development is consisting of elevated station that has reached 94.42 percent, underground station has reached 97.53 percent, and depot and elevated section has reached 94.42 percent

The phase I MRT development that connects Lebak Bulus to HI Roundabout today, has reached 95.97 percent.

"Physical development is consisting of elevated station that has reached 94.42 percent, underground station has reached 97.53 percent, and depot and elevated section has reached 94.42 percent," disclosed MRT Jakarta President Director, William P Sabandar, Tuesday (8/28).

Anies Rides MRT Trains from Lebak Bulus towards HI

If it is calculated with operation time, his party still has 184 days to prepare for any shortcomings.

"Hopefully everything can run smoothly and well," he hoped.

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye870 personTiyo Surya Sakti
  2. South Jakarta Tackles 38 Dengue Cases to Prevent Outbreak

    access_time02-02-2026 remove_red_eye522 personTiyo Surya Sakti
  3. TransJabodetabek Expansion, a Strategic Step to Increase Public Transportation Use

    access_time26-01-2026 remove_red_eye430 personFakhrizal Fakhri
  4. Jakarta Prepares OMC and 200 Excavators to Prevent Flood

    access_time26-01-2026 remove_red_eye373 personDessy Suciati
  5. Several Microtrans Routes Diverted

    access_time31-01-2026 remove_red_eye363 personAldi Geri Lumban Tobing
close