Progress in Repairing Sunter River's Retaining Wall Reaches 75 Percent

Sunter River's retaining wall repair that is located at RT 12/13, Cipinang Muara, Jatinegara, East Jakarta has reached 75 percent, on Thursday (3/12). Water level on the river often rises thus it inhibits the repair.

We repair it using river stones and piles of dolken woods

Jatinegara Water Resources (SDA) Unit personnel, Tamrizal conveyed, his side has started the repair since end of February.

"Retaining wall as long as 30 meters with height of 4 meters was collapsed thus we repair it using river stones and piles of dolken woods," he said.

Krukut River's Retaining Wall in Pela Mampang Repaired

He couldn't tell when the repair could be finished because he had to stop the work when water level rose. Besides, his side needs to share the material with other units who repair another retaining walls in different locations in East Jakarta.

"We only repair it temporarily to prevent it from collapsing again. Only BBWSCC that has the authority to install the sheet piles and repair it permanently," he conveyed.

Linked News
Popular News indeks
  1. 1,262 Personnel Ready to Support Bhayangkara Anniversary Cleanliness

    access_time30-06-2025 remove_red_eye584 personAldi Geri Lumban Tobing
  2. 4,072 Damaged Roads in Central Jakarta Have Been Repaired

    access_time04-07-2025 remove_red_eye363 personFolmer
  3. Dishub Pushes Digitization of Parking Management for Local Revenue

    access_time01-07-2025 remove_red_eye298 personFakhrizal Fakhri
  4. Pramono Asks for Onrust Island Tourism Potential to Be Optimized

    access_time04-07-2025 remove_red_eye251 personDessy Suciati
  5. Transjabodetabek Bekasi-Galunggung Route Officially Operates

    access_time03-07-2025 remove_red_eye248 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik