Perbaikan Turap Longsor Kali Sunter di Cipinang Muara Capai 75 Persen

Progress in Repairing Sunter River's Retaining Wall Reaches 75 Percent

Sunter River's retaining wall repair that is located at RT 12/13, Cipinang Muara, Jatinegara, East Jakarta has reached 75 percent, on Thursday (3/12). Water level on the river often rises thus it inhibits the repair.

We repair it using river stones and piles of dolken woods

Jatinegara Water Resources (SDA) Unit personnel, Tamrizal conveyed, his side has started the repair since end of February.

"Retaining wall as long as 30 meters with height of 4 meters was collapsed thus we repair it using river stones and piles of dolken woods," he said.

Krukut River's Retaining Wall in Pela Mampang Repaired

He couldn't tell when the repair could be finished because he had to stop the work when water level rose. Besides, his side needs to share the material with other units who repair another retaining walls in different locations in East Jakarta.

"We only repair it temporarily to prevent it from collapsing again. Only BBWSCC that has the authority to install the sheet piles and repair it permanently," he conveyed.

Linked News
Popular News indeks
  1. Attending Betawi Eid 2026, Pram Encourages Strengthening Cultural Values

    access_time11-04-2026 remove_red_eye1060 personFolmer
  2. Low Emission Zones: Jakarta’s Concrete Step to Curb Air Pollution

    access_time13-04-2026 remove_red_eye891 personAldi Geri Lumban Tobing
  3. Posyandu-Posbindu Services Reach 1,600 Seniors and Toddlers in Utan Panjang

    access_time07-04-2026 remove_red_eye845 personFolmer
  4. Jakpro Promotes Integration Between JIS and KRL Station

    access_time10-04-2026 remove_red_eye837 personAldi Geri Lumban Tobing
  5. Cilandak Health Center Maintains Optimal Services

    access_time10-04-2026 remove_red_eye806 personTiyo Surya Sakti